United States › Grid › Interconnection queues › Wyoming

ONSHORE WIND · WEST

Onshore wind project 836, Carbon County

Onshore wind project 836, Carbon County is a 400 MW onshore wind request with a signed interconnection agreement in the West interconnection queue, in Carbon County, Wyoming, connecting to PacifiCorp.

Queue statusConsented
  1. PlanningQueued Dec 2016 (completed)
  2. ConsentedMar 2020 (current stage)
  3. Construction (not yet reached)
  4. OperatingTarget Dec 2027 (not yet reached)
  5. Closed (not yet reached)

Request details

Queue ID
836
Grid region
West (non-ISO utilities)
Utility / transmission owner
PacifiCorp
Developer
PacifiCorp
Connection point (POI)
Aeolus substation
Location
Carbon County, Wyoming
Technology
Wind: 400 MW
Total requested
400 MW
Service type
Energy only (ERIS)
Study phase
IA executed 3/25/2020
Queue status
Active
Entered queue
5 December 2016
Agreement signed
25 March 2020
Proposed online date
December 2027

Location

Marker shows the centre of Carbon County; the queue data does not give exact sites.

Power plants in Wyoming · Transmission lines in Wyoming

Other requests in Carbon County