Withdrawn queue requests in the USA (2025 requests) โ€” page 3

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown47497.1 GW
Active in queue452.0 GW1,836 requests
Agreement signed4,701 MW27 requests
Withdrawn47497.1 GW never built

Map

Loading requestsโ€ฆ
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

474 requests ยท page 3 of 10
ProjectCapacityStatusLocationRegionQueuedOnline
Battery storage project 25-IC-1332, Oglethorpe County
Battery storage
250 MWWithdrawn / abandoned Oglethorpe, GASoutheast Apr 2025
Onshore wind project GEN-2024-195, Edwards County
Onshore wind
250 MWWithdrawn / abandoned Edwards, KSSPP Mar 2025target 2028
Onshore wind project AH1-670, Mclean County
Onshore wind ยท Wapella Bluffs Wind Project, LLC
250 MWWithdrawn / abandoned Mclean, ILPJM Feb 2025
Solar project AG2-404, Hardy County
Solar ยท Old Fields Solar, LLC
250 MWWithdrawn / abandoned Hardy, WVPJM Jan 2025target 2024
Onshore wind project GEN-2024-111, Washita County
Onshore wind
250 MWWithdrawn / abandoned Washita, OKSPP Mar 2025target 2031
Onshore wind project GEN-2024-197, Edwards County
Onshore wind
250 MWWithdrawn / abandoned Edwards, KSSPP Mar 2025target 2028
Battery storage project 761, Elmore County
Battery storage
250 MWWithdrawn / abandoned Elmore, IDWest Apr 2025
Solar + storage project IA-PNM-2025-08, Curry County
Solar + storage
250 MWWithdrawn / abandoned Curry, NMWest Mar 2025target 2028
Solar + storage project GEN-2024-350, Roosevelt County
Solar + storage
250 MWWithdrawn / abandoned Roosevelt, NMSPP Mar 2025target 2029
Solar project GEN-2024-146, Craig County
Solar
250 MWWithdrawn / abandoned Craig, OKSPP Mar 2025target 2031
Onshore wind project GEN-2024-202, Hyde County
Onshore wind
250 MWWithdrawn / abandoned Hyde, SDSPP Mar 2025target 2030
King Cabbage Solar
Solar ยท ACE DevCo NC, LLC
250 MWWithdrawn / abandoned ERCOT Feb 2025target 2028
Onshore wind project GEN-2024-290, Pittsburg County
Onshore wind
250 MWWithdrawn / abandoned Pittsburg, OKSPP Mar 2025target 2030
Solar project J3934, Mcleod County
Solar
250 MWWithdrawn / abandoned Mcleod, MNMISO Feb 2025target 2029
Solar + storage project GEN-2024-262, Lea County
Solar + storage
250 MWWithdrawn / abandoned Lea, NMSPP Mar 2025target 2029
Wind + storage project IA-PNM-2025-14, Torrance County
Wind + storage
250 MWWithdrawn / abandoned Torrance, NMWest Mar 2025target 2030
Onshore wind project GEN-2024-223, Dawson County
Onshore wind
241 MWWithdrawn / abandoned Dawson, MTSPP Mar 2025target 2030
McKean County Solar II
Solar ยท RWE Solar Development, LLC
240 MWWithdrawn / abandoned Mckean, PAPJM Jan 2025target 2024
Onshore wind project J3956, Wilkin County
Onshore wind
240 MWWithdrawn / abandoned Wilkin, MNMISO Apr 2025target 2030
Lewis Run - Pierce Brook 230 kV
Solar ยท RWE Solar Development, LLC
240 MWWithdrawn / abandoned Mckean, PANYISO Sep 2025
Battery storage project AG2-451, Salem County
Battery storage ยท Carneys Point Energy Storage, L.L.C.
240 MWWithdrawn / abandoned Salem, NJPJM Mar 2025target 2024
Onshore wind project GEN-2024-237, Okfuskee County
Onshore wind
240 MWWithdrawn / abandoned Okfuskee, OKSPP Mar 2025target 2029
Other project Q613, Maricopa County
Other
232 MWWithdrawn / abandoned Maricopa, AZWest May 2025target 2026
Solar project GEN-2024-387
Solar
225 MWWithdrawn / abandoned SPP Mar 2025target 2031
Solar project GEN-2024-388, Tillman County
Solar
225 MWWithdrawn / abandoned Tillman, OKSPP Mar 2025target 2031
Battery storage project 25-IC-1346, Polk County
Battery storage
225 MWWithdrawn / abandoned Polk, GASoutheast Apr 2025
Solar project AH1-234, Winnebago County
Solar ยท Gemini Solar LLC
224 MWWithdrawn / abandoned Winnebago, ILPJM Mar 2025target 2025
Onshore wind project GEN-2024-101, Finney County
Onshore wind
220 MWWithdrawn / abandoned Finney, KSSPP Mar 2025target 2031
Battery storage project AG2-450, Gloucester County
Battery storage ยท Logan Energy Storage, L.L.C.
219 MWWithdrawn / abandoned Gloucester, NJPJM Mar 2025target 2025
Solar project J3951, Polk County
Solar
218 MWWithdrawn / abandoned Polk, MNMISO Feb 2025target 2030
Solar project J3893, Phillips County
Solar
214 MWWithdrawn / abandoned Phillips, ARMISO Feb 2025target 2030
Solar project AG2-658, Webster County
Solar ยท Halo Solar WV LLC
210 MWWithdrawn / abandoned Webster, WVPJM Jan 2025target 2024
Battery storage project Q2508, Maricopa County
Battery storage
206 MWWithdrawn / abandoned Maricopa, AZWest Feb 2025target 2029
Onshore wind project APP-100087
Onshore wind
203 MWWithdrawn / abandoned NDMISO Aug 2025
Solar project GEN-2024-147, Eddy County
Solar
200 MWWithdrawn / abandoned Eddy, NMSPP Mar 2025target 2029
Battery storage project AG2-331, Decatur County
Battery storage ยท Cobia Solar LLC
200 MWWithdrawn / abandoned Decatur, INPJM Feb 2025target 2024
Solar + storage project 2025-G2
Solar + storage
200 MWWithdrawn / abandoned West Feb 2025target 2027
Solar + storage project IA-PNM-2025-07, Luna County
Solar + storage
200 MWWithdrawn / abandoned Luna, NMWest Mar 2025target 2028
Battery storage project J4192, Racine County
Battery storage
200 MWWithdrawn / abandoned Racine, WIMISO Oct 2025target 2029
Solar project J3885, Morehouse Parish County
Solar
200 MWWithdrawn / abandoned Morehouse Parish, LAMISO Feb 2025target 2030
Solar project GEN-2024-155, Cherokee County
Solar
200 MWWithdrawn / abandoned Cherokee, TXSPP Mar 2025target 2029
Onshore wind project GEN-2024-238, Craig County
Onshore wind
200 MWWithdrawn / abandoned Craig, OKSPP Mar 2025target 2029
Onshore wind project J4064, Tallahatchie County
Onshore wind
200 MWWithdrawn / abandoned Tallahatchie, MSMISO Sep 2025target 2030
Solar + storage project 780, Ada County
Solar + storage
200 MWWithdrawn / abandoned Ada, IDWest Apr 2025
Solar project AG2-212, Marshall County
Solar ยท Wahoo Solar LLC
200 MWWithdrawn / abandoned Marshall, INPJM Feb 2025target 2024
Onshore wind project GEN-2024-094, Meade County
Onshore wind
200 MWWithdrawn / abandoned Meade, KSSPP Mar 2025target 2028
Onshore wind project J3972, Liberty County
Onshore wind
200 MWWithdrawn / abandoned Liberty, TXMISO Mar 2025target 2029
Farmers Valley โ€šร„รฌ Ridgeway 115 kV
Solar ยท RWE Solar Development, LLC
200 MWWithdrawn / abandoned Mckean, PANYISO Sep 2025
Solar project GEN-2024-106, Lamb County
Solar
200 MWWithdrawn / abandoned Lamb, TXSPP Mar 2025target 2031
Solar project AH1-147, Ogle County
Solar ยท Mound Solar, LLC
200 MWWithdrawn / abandoned Ogle, ILPJM Feb 2025target 2025

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines ยท Planned power plants (EIA)