United States βΊ Grid βΊ Interconnection queues βΊ Georgia
BATTERY STORAGE Β· SOUTHEASTBattery storage project 25-IC-1332, Oglethorpe County
Battery storage project 25-IC-1332, Oglethorpe County is a 250 MW battery storage request withdrawn in the Southeast interconnection queue, in Oglethorpe County, Georgia, connecting to Southern Company.
Queue statusWithdrawn / abandoned
- PlanningQueued Apr 2025 (completed)
- Withdrawn / abandonedDec 2025 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- 25-IC-1332
- Grid region
- Southeast (non-ISO utilities)
- Utility / transmission owner
- Southern Company
- Connection point (POI)
- Goose Pond Road Substation 230 kV Bus
- Location
- Oglethorpe County, Georgia
- Technology
- Battery: 250 MW
- Total requested
- 250 MW
- Service type
- Energy only (ERIS)
- Study phase
- Withdrawn
- Queue status
- Withdrawn
- Entered queue
- 14 April 2025
- Withdrawn
- December 2025
Location
Marker shows the centre of Oglethorpe County; the queue data does not give exact sites.
Other requests in Oglethorpe County
- Solar project IC-769, Oglethorpe CountySolar Β· 60.0 MW Β· agreement signed
- Solar project IC-762, Oglethorpe CountySolar Β· 38.0 MW Β· agreement signed
- Solar + storage project IC-1013, Oglethorpe CountySolar + storage Β· 200 MW Β· suspended
- Solar project IC-988, Oglethorpe CountySolar Β· 120 MW Β· suspended
- Solar + storage project IC-980, Oglethorpe CountySolar + storage Β· 100 MW Β· suspended
- Solar project IC-352, Oglethorpe CountySolar Β· 100 MW Β· withdrawn
- Solar project IC-363, Oglethorpe CountySolar Β· 78.0 MW Β· withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem