United States β€Ί Grid β€Ί Interconnection queues β€Ί New Mexico

WIND + STORAGE Β· WEST

Wind + storage project IA-PNM-2025-14, Torrance County

Wind + storage project IA-PNM-2025-14, Torrance County is a 250 MW wind + storage request withdrawn in the West interconnection queue, in Torrance County, New Mexico, connecting to Public Service Company of New Mexico.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Mar 2025 (completed)
  2. Withdrawn / abandoned (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
IA-PNM-2025-14
Grid region
West (non-ISO utilities)
Utility / transmission owner
Public Service Company of New Mexico
Connection point (POI)
Western Spirit 345 kV Switchyard to Abo
Location
Torrance County, New Mexico
Technology
Wind: 250 MW Β· Battery
Total requested
250 MW
Service type
Network resource (NRIS)
Queue status
Withdrawn
Entered queue
21 March 2025
Proposed online date
December 2030

Location

Marker shows the centre of Torrance County; the queue data does not give exact sites.

Power plants in New Mexico Β· Transmission lines in New Mexico

Other requests in Torrance County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem