United States › Grid › Interconnection queues

OCTARY USA · INTERCONNECTION QUEUES

Withdrawn queue requests in the USA (2024 requests) — page 3

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown1,313251.4 GW
Active in queue285.2 GW1,283 requests
Agreement signed30.3 GW117 requests
Withdrawn1,313251.4 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

1,313 requests · page 3 of 27
ProjectCapacityStatusLocationRegionQueuedOnline
Kiskadee Trail Storage SLF
Battery storage · Kiskadee Trail Storage, LLC
406 MWWithdrawn / abandoned ERCOT Oct 2024target 2029
Kiskadee Trail Solar SLF
Solar · Kiskadee Trail Solar, LLC
406 MWWithdrawn / abandoned ERCOT Oct 2024target 2029
Solar project J3760, Richland Parish County
Solar
405 MWWithdrawn / abandoned Richland Parish, LAMISO Apr 2024target 2028
Onshore wind project C4-020, San Juan County
Onshore wind
402 MWWithdrawn / abandoned San Juan, UTWest May 2024target 2028
Austin Bayou Solar II
Solar · Austin Bayou Solar, LLC
402 MWWithdrawn / abandoned Brazoria, TXERCOT Mar 2024target 2027
Firefly Power
Battery storage · Firefly Power LLC
401 MWWithdrawn / abandoned Tarrant, TXERCOT Feb 2024target 2027
Battery storage project 626, Indian River County
Battery storage · FPL
400 MWWithdrawn / abandoned Indian River, FLSoutheast Jan 2024target 2033
Battery storage project 623, Okeechobee County
Battery storage · FPL
400 MWWithdrawn / abandoned Okeechobee, FLSoutheast Jan 2024target 2030
Solar project J3303, Prairie County
Solar
400 MWWithdrawn / abandoned Prairie, ARMISO Apr 2024target 2027
Black Cherry BESS
Battery storage · Black Cherry Wind Power, LLC
400 MWWithdrawn / abandoned Mckean, PANYISO Oct 2024
Solar project J3349, Fulton County
Solar
400 MWWithdrawn / abandoned Fulton, ILMISO Apr 2024target 2028
Battery storage project J3311, St. Landry Parish County
Battery storage
400 MWWithdrawn / abandoned St. Landry Parish, LAMISO Apr 2024target 2027
Solar project 167, Cochise County
Solar
400 MWWithdrawn / abandoned Cochise, AZWest Apr 2024target 2029
Solar + storage project 172, Cochise County
Solar + storage
400 MWWithdrawn / abandoned Cochise, AZWest Jun 2024target 2028
Battery storage project J3488, Vermillion County
Battery storage
400 MWWithdrawn / abandoned Vermillion, INMISO Apr 2024target 2028
Battery storage project 627, Martin County
Battery storage · FPL
400 MWWithdrawn / abandoned Martin, FLSoutheast Jan 2024target 2031
Solar project J3388, Calhoun County
Solar
400 MWWithdrawn / abandoned Calhoun, ARMISO Apr 2024target 2028
Green Isles Energy Storage
Battery storage · CEDAR HOLDCO LLC
400 MWWithdrawn / abandoned Suffolk, NYNYISO Oct 2024
Solar project J3409, Newton County
Solar
400 MWWithdrawn / abandoned Newton, TXMISO Apr 2024target 2028
Battery storage project 608, Desoto County
Battery storage
400 MWWithdrawn / abandoned Desoto, MSSoutheast Jan 2024
Solar + storage project C4-023, Utah County
Solar + storage
400 MWWithdrawn / abandoned Utah, UTWest May 2024target 2030
Bayonne Energy Storage II
Battery storage · AMBAR POWER HOLDCO LLC
400 MWWithdrawn / abandoned Hudson, NJNYISO Oct 2024
Solar project J3540, Monroe County
Solar
400 MWWithdrawn / abandoned Monroe, ARMISO Apr 2024target 2028
Battery storage project 628, Martin County
Battery storage · FPL
400 MWWithdrawn / abandoned Martin, FLSoutheast Jan 2024target 2031
Battery storage project J3728, Franklin County
Battery storage
400 MWWithdrawn / abandoned Franklin, ILMISO Apr 2024target 2028
Gas project C4-030, Power County
Gas
400 MWWithdrawn / abandoned Power, IDWest May 2024target 2030
PA-Hockenberry LLC
Solar · PA-Hockenberry LLC
400 MWWithdrawn / abandoned Jefferson, PANYISO Sep 2024
Solar project J3711, Calhoun County
Solar
400 MWWithdrawn / abandoned Calhoun, ARMISO Apr 2024target 2029
Onshore wind project C4-085, Carbon County
Onshore wind
400 MWWithdrawn / abandoned Carbon, WYWest May 2024target 2029
Solar project J3487, Vermillion County
Solar
400 MWWithdrawn / abandoned Vermillion, INMISO Apr 2024target 2028
Solar + storage project C4-034, Emery County
Solar + storage
400 MWWithdrawn / abandoned Emery, UTWest May 2024target 2030
Solar + storage project C4-089, Utah County
Solar + storage
400 MWWithdrawn / abandoned Utah, UTWest May 2024target 2027
Battery storage project J3509, Sangamon County
Battery storage
380 MWWithdrawn / abandoned Sangamon, ILMISO Apr 2024target 2027
Arthur Kill Upgrade
Gas · Arthur Kill Power
370 MWWithdrawn / abandoned Richmond, NYNYISO Oct 2024
Battery Storage
Battery storage
366 MWWithdrawn / abandoned Franklin, MAISO-NE Apr 2024target 2028
5Mile Storage Project
Battery storage · Five Mile Energy, LLC
360 MWWithdrawn / abandoned Cattaraugus, NYNYISO Oct 2024
Savanna Prairie Solar
Solar · Savanna Prairie Solar, LLC
355 MWWithdrawn / abandoned ERCOT Oct 2024target 2028
Snowy Knoll Wind Project
Wind + storage · Snowy Knoll Wind Project, LLC
350 MWWithdrawn / abandoned Oneida, NYNYISO Sep 2024
Solar project J3255, Holmes County
Solar
350 MWWithdrawn / abandoned Holmes, MSMISO Apr 2024target 2028
Wheelhouse Solar Energy Center
Solar + storage · Wheelhouse Solar Energy Center, LLC
350 MWWithdrawn / abandoned Herkimer, NYNYISO Sep 2024
West Laurens
Solar · ACE DevCo NC, LLC
350 MWWithdrawn / abandoned Otsego, NYNYISO Sep 2024
Solar project J3304, Clark County
Solar
350 MWWithdrawn / abandoned Clark, ARMISO Apr 2024target 2027
Solar project J3482, Mclean County
Solar
350 MWWithdrawn / abandoned Mclean, ILMISO Apr 2024target 2028
Black Cherry Wind 1
Onshore wind · Black Cherry Wind Power, LLC
350 MWWithdrawn / abandoned Cameron, PANYISO Sep 2024
Solar + storage project C4-042, Carbon County
Solar + storage
330 MWWithdrawn / abandoned Carbon, WYWest May 2024target 2029
Ez Energy Solutions LLC 5802 BESS
Battery storage · EZ ENERGY SOLUTIONS LLC
329 MWWithdrawn / abandoned Kings, NYNYISO Oct 2024
Solar project J3322, Jefferson Davis Parish County
Solar
325 MWWithdrawn / abandoned Jefferson Davis Parish, LAMISO Apr 2024target 2028
Adams Brook Storage
Other · Adams Creek Solar Project, LLC
314 MWWithdrawn / abandoned Wilbarger, TXERCOT Feb 2024target 2027
Battery Storage
Battery storage
313 MWWithdrawn / abandoned Washington, RIISO-NE Jun 2024target 2027
Onshore wind project C4-036, Carbon County
Onshore wind
310 MWWithdrawn / abandoned Carbon, WYWest May 2024target 2031
Page 3 of 27

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)