United States › Grid › Interconnection queues › New Jersey
BATTERY STORAGE · NYISOBayonne Energy Storage II
Bayonne Energy Storage II is a 400 MW battery storage request withdrawn in the NYISO interconnection queue, in Hudson County, New Jersey, connecting to ConED.
Queue statusWithdrawn / abandoned
- PlanningQueued Oct 2024 (completed)
- Withdrawn / abandoned (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- C24-355
- Grid region
- NYISO (New York)
- Utility / transmission owner
- ConED
- Developer
- AMBAR POWER HOLDCO LLC
- Connection point (POI)
- Gowanus Substation 345 kV
- Location
- Hudson County, New Jersey
- Technology
- Battery: 400 MW
- Total requested
- 400 MW
- Queue status
- Withdrawn
- Entered queue
- 15 October 2024
Location
Marker shows the centre of Hudson County; the queue data does not give exact sites.
Power plants in New Jersey · Transmission lines in New Jersey
Other requests in Hudson County
- Hudson Energy Storage FacilityBattery storage · 200 MW · agreement signed
- Two Rivers StorageBattery storage · 150 MW · agreement signed
- Bayonne Energy CenterGas · 500 MW · built
- Bayonne Energy CenterGas · 500 MW · built
- Kearny #13Gas · 178 MW · built
- Kearny #12Gas · 168 MW · built
- Bayonne Energy Center IIGas · 129 MW · built
- Bayonne Energy Center IIGas · 129 MW · built
- Kearny #14Gas · 89.0 MW · built
- Kearny Generating StationGas · 40.0 MW · built
- Hudson Generating StationCoal · 24.0 MW · built
- Kearny Generating StationGas · 24.0 MW · built
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem