Solar + storage project C4-042, Carbon County

Solar + storage project C4-042, Carbon County is a 330 MW solar + storage request withdrawn in the West interconnection queue, in Carbon County, Wyoming, connecting to PacifiCorp.

Queue statusWithdrawn / abandoned
  1. PlanningQueued May 2024 (completed)
  2. Withdrawn / abandoned (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
C4-042
Grid region
West (non-ISO utilities)
Utility / transmission owner
PacifiCorp
Connection point (POI)
Platte substation
Location
Carbon County, Wyoming
Technology
Solar: 330 MW Β· Battery
Total requested
330 MW
Service type
NRIS and ERIS
Queue status
Withdrawn
Entered queue
15 May 2024
Proposed online date
January 2029

Location

Marker shows the centre of Carbon County; the queue data does not give exact sites.

Power plants in Wyoming Β· Transmission lines in Wyoming

Other requests in Carbon County