Wheelhouse Solar Energy Center

Wheelhouse Solar Energy Center is a 350 MW solar + storage request withdrawn in the NYISO interconnection queue, in Herkimer County, New York, connecting to NYPA.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Sep 2024 (completed)
  2. Withdrawn / abandoned (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
C24-188
Grid region
NYISO (New York)
Utility / transmission owner
NYPA
Developer
Wheelhouse Solar Energy Center, LLC
Connection point (POI)
Edic 345 kV to Princetown 345 kV circuit #352
Location
Herkimer County, New York
Technology
Solar: 350 MW · Battery
Total requested
350 MW
Queue status
Withdrawn
Entered queue
18 September 2024

Location

Marker shows the centre of Herkimer County; the queue data does not give exact sites.