United States › Grid › Interconnection queues › Pennsylvania
ONSHORE WIND · NYISOBlack Cherry Wind 1
Black Cherry Wind 1 is a 350 MW onshore wind request withdrawn in the NYISO interconnection queue, in Cameron County, Pennsylvania, connecting to NYSEG.
Queue statusWithdrawn / abandoned
- PlanningQueued Sep 2024 (completed)
- Withdrawn / abandoned (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- C24-298
- Grid region
- NYISO (New York)
- Utility / transmission owner
- NYSEG
- Developer
- Black Cherry Wind Power, LLC
- Connection point (POI)
- Homer City - Piercebrook 345kV
- Location
- Cameron County, Pennsylvania
- Technology
- Wind: 350 MW
- Total requested
- 350 MW
- Queue status
- Withdrawn
- Entered queue
- 29 September 2024
Location
Marker shows the centre of Cameron County; the queue data does not give exact sites.
Power plants in Pennsylvania · Transmission lines in Pennsylvania
Other requests in Cameron County
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem