United States โบ Grid โบ Interconnection queues
OCTARY USA ยท INTERCONNECTION QUEUESWithdrawn queue requests in the USA (2014 requests) โ page 3
Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.
Map
Requests
| Project | Capacity | Status |
|---|---|---|
| Johanna Energy Center (Fka Johanna Energy Center LMS) Gas |
220 MW | Withdrawn / abandoned |
| Solar project IC-346, Glynn County Solar |
215 MW | Withdrawn / abandoned |
| Solar project IC-349, Jeff Davis County Solar |
215 MW | Withdrawn / abandoned |
| Onshore wind project AA1-103, Carbon County Onshore wind |
209 MW | Withdrawn / abandoned |
| Gas project Z2-084, Nelson County Gas |
208 MW | Withdrawn / abandoned |
| Other project Z2-072 Other |
205 MW | Withdrawn / abandoned |
| Gas project J398, Marquette County Gas |
204 MW | Withdrawn / abandoned |
| Gas project GEN-2014-068, Deaf Smith County Gas |
203 MW | Withdrawn / abandoned |
| Lighthouse Wind Onshore wind ยท Lighthouse Wind, LLC |
201 MW | Withdrawn / abandoned |
| Onshore wind project J346, Nodaway County Onshore wind |
201 MW | Withdrawn / abandoned |
| San Roman Wind 2 Onshore wind ยท Pioneer Green |
201 MW | Withdrawn / abandoned |
| Red River Saltfork W Onshore wind ยท Chermac |
201 MW | Withdrawn / abandoned |
| Onshore wind project GI-1412, Billings County Onshore wind |
201 MW | Withdrawn / abandoned |
| Watusi Wind, LLC Onshore wind ยท NextEra Energy Resources |
201 MW | Withdrawn / abandoned |
| Onshore wind project GEN-2014-062, Kiowa County Onshore wind |
200 MW | Withdrawn / abandoned |
| Onshore wind project GEN-2014-049, Pratt County Onshore wind |
200 MW | Withdrawn / abandoned |
| Onshore wind project GEN-2014-052, Beaver County Onshore wind |
200 MW | Withdrawn / abandoned |
| Onshore wind project GEN-2014-073, Hale County Onshore wind |
200 MW | Withdrawn / abandoned |
| Onshore wind project GEN-2014-038, Hansford County Onshore wind |
200 MW | Withdrawn / abandoned |
| Solar project GI-1402, Meade County Solar |
200 MW | Withdrawn / abandoned |
| Onshore wind project J408, Sanilac County Onshore wind |
200 MW | Withdrawn / abandoned |
| Onshore wind project GEN-2014-037, Texas County Onshore wind |
200 MW | Withdrawn / abandoned |
| Onshore wind project GEN-2014-072, Rush County Onshore wind |
200 MW | Withdrawn / abandoned |
| Onshore wind project Company GA, Elko County Onshore wind |
200 MW | Withdrawn / abandoned |
| Solar project J368, Lee County Solar |
200 MW | Withdrawn / abandoned |
| WIT Ranch Wind Onshore wind ยท Eon |
200 MW | Withdrawn / abandoned |
| Onshore wind project AA1-086, Macon County Onshore wind |
200 MW | Withdrawn / abandoned |
| Onshore wind project Z2-086, Adams County Onshore wind |
200 MW | Withdrawn / abandoned |
| Onshore wind project J415, Franklin County Onshore wind |
200 MW | Withdrawn / abandoned |
| Onshore wind project 614, San Juan County Onshore wind |
199 MW | Withdrawn / abandoned |
| Buffalo Wind 2 Onshore wind ยท National Renewable Solutions |
199 MW | Withdrawn / abandoned |
| Solar project J380, Lee County Solar |
199 MW | Withdrawn / abandoned |
| Onshore wind project 262, Gibson County Onshore wind |
198 MW | Withdrawn / abandoned |
| Gas project AA1-036, Luzerne County Gas |
180 MW | Withdrawn / abandoned |
| Onshore wind project Z2-042, Pulaski County Onshore wind |
180 MW | Withdrawn / abandoned |
| Onshore wind project GEN-2014-051, Nemaha County Onshore wind |
174 MW | Withdrawn / abandoned |
| Gas project GEN-2014-011, Mcpherson County Gas |
172 MW | Withdrawn / abandoned |
| Gateway Bradford Plant Gas |
163 MW | Withdrawn / abandoned |
| Onshore wind project GEN-2014-061, Blaine County Onshore wind |
161 MW | Withdrawn / abandoned |
| Onshore wind project GEN-2014-059, Keith County Onshore wind |
160 MW | Withdrawn / abandoned |
| Onshore wind project GEN-2014-055, Wayne County Onshore wind |
160 MW | Withdrawn / abandoned |
| SLW (Fka Shu'Luuk Wind) Onshore wind |
160 MW | Withdrawn / abandoned |
| Other project AA1-016, Monroe County Other |
158 MW | Withdrawn / abandoned |
| Deepwater Gas |
158 MW | Withdrawn / abandoned |
| Other project Z2-053 Other |
156 MW | Withdrawn / abandoned |
| Gas project J397, Marquette County Gas |
153 MW | Withdrawn / abandoned |
| Onshore wind project GEN-2014-074, Floyd County Onshore wind |
152 MW | Withdrawn / abandoned |
| Solar project IC-374, Putnam County Solar |
151 MW | Withdrawn / abandoned |
| Onshore wind project J321, Sanilac County Onshore wind |
151 MW | Withdrawn / abandoned |
| Horseshoe Bend S Solar ยท Luminant |
150 MW | Withdrawn / abandoned |
Capacity in the queue by state
Click a state to drill down.
By grid region
ISO/RTO markets and the non-ISO West and Southeast.
- MISO (Midcontinent)77 ยท 22.8 GW
- PJM (Mid-Atlantic, Midwest)126 ยท 12.4 GW
- ERCOT (Texas)52 ยท 12.1 GW
- CAISO (California)70 ยท 10.2 GW
- West (non-ISO utilities)151 ยท 9,551 MW
- SPP (Southwest Power Pool)56 ยท 8,704 MW
- Southeast (non-ISO utilities)76 ยท 6,064 MW
- ISO-NE (New England)28 ยท 4,881 MW
- NYISO (New York)30 ยท 1,581 MW
Requests by year joined
Capacity of requests in this view, by the year they entered the queue. Click a year.
Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines ยท Planned power plants (EIA)