ONSHORE WIND Β· SPP

Onshore wind project GEN-2014-052, Beaver County

Onshore wind project GEN-2014-052, Beaver County is a 200 MW onshore wind request withdrawn in the SPP interconnection queue, in Beaver County, Oklahoma, connecting to OGE.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Sep 2014 (completed)
  2. Withdrawn / abandonedMar 2015 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
GEN-2014-052
Grid region
SPP (Southwest Power Pool)
Utility / transmission owner
OGE
Connection point (POI)
Tap Hitchland - Woodward Dbl Ckt (GEN-2011-014 Tap) 345kV
Location
Beaver County, Oklahoma
Technology
Wind: 200 MW
Total requested
200 MW
Service type
Energy only (ERIS)
Study phase
WITHDRAWN
Queue status
Withdrawn
Entered queue
29 September 2014
Proposed online date
December 2016
Withdrawn
March 2015

Location

Marker shows the centre of Beaver County; the queue data does not give exact sites.

Power plants in Oklahoma Β· Transmission lines in Oklahoma

Other requests in Beaver County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem