United States › Grid › Interconnection queues › Oklahoma

ONSHORE WIND · SPP

Onshore wind project GEN-2017-047, Beaver County

Onshore wind project GEN-2017-047, Beaver County is a 102 MW onshore wind request built and operating in the SPP interconnection queue, in Beaver County, Oklahoma, connecting to SPS.

Queue statusOperating
  1. PlanningQueued May 2017 (completed)
  2. Consented (completed)
  3. Construction (completed)
  4. OperatingDec 2024 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
GEN-2017-047
Grid region
SPP (Southwest Power Pool)
Utility / transmission owner
SPS
Connection point (POI)
Bull Creek 115 kV substation
Location
Beaver County, Oklahoma
Technology
Wind: 102 MW
Total requested
102 MW
Service type
NRIS and ERIS
Study phase
IA FULLY EXECUTED/COMMERCIAL OPERATION
Queue status
Operational
Entered queue
18 May 2017
Proposed online date
December 2024
Came online
December 2024

Location

Marker shows the centre of Beaver County; the queue data does not give exact sites.

Power plants in Oklahoma · Transmission lines in Oklahoma

Other requests in Beaver County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem