United States › Grid › Interconnection queues › Oklahoma

ONSHORE WIND · SPP

Onshore wind project GEN-2008-047, Beaver County

Onshore wind project GEN-2008-047, Beaver County is a 263 MW onshore wind request built and operating in the SPP interconnection queue, in Beaver County, Oklahoma, connecting to OGE.

Queue statusOperating
  1. PlanningQueued May 2008 (completed)
  2. Consented (completed)
  3. Construction (completed)
  4. OperatingDec 2014 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
GEN-2008-047
Grid region
SPP (Southwest Power Pool)
Utility / transmission owner
OGE
Connection point (POI)
Hitchland-Woodward EHV Dbl Ckt (Beaver County) 345kV
Location
Beaver County, Oklahoma
Technology
Wind: 263 MW
Total requested
263 MW
Service type
Energy only (ERIS)
Study phase
IA FULLY EXECUTED/COMMERCIAL OPERATION
Queue status
Operational
Entered queue
16 May 2008
Proposed online date
December 2014
Came online
December 2014

Location

Marker shows the centre of Beaver County; the queue data does not give exact sites.

Power plants in Oklahoma · Transmission lines in Oklahoma

Other requests in Beaver County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem