United States β€Ί Grid β€Ί Interconnection queues β€Ί Oklahoma

ONSHORE WIND Β· SPP

Onshore wind project GEN-2014-037, Texas County

Onshore wind project GEN-2014-037, Texas County is a 200 MW onshore wind request withdrawn in the SPP interconnection queue, in Texas County, Oklahoma, connecting to SPS.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Sep 2014 (completed)
  2. Withdrawn / abandonedJan 2019 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
GEN-2014-037
Grid region
SPP (Southwest Power Pool)
Utility / transmission owner
SPS
Connection point (POI)
Beaver County-Hitchland Dbl Ckt (Optima) 345kV
Location
Texas County, Oklahoma
Technology
Wind: 200 MW
Total requested
200 MW
Service type
Energy only (ERIS)
Study phase
WITHDRAWN
Queue status
Withdrawn
Entered queue
30 September 2014
Proposed online date
September 2017
Withdrawn
January 2019

Location

Marker shows the centre of Texas County; the queue data does not give exact sites.

Power plants in Oklahoma Β· Transmission lines in Oklahoma

Other requests in Texas County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem