ONSHORE WIND · CAISO

SLW (Fka Shu'Luuk Wind)

SLW (Fka Shu'Luuk Wind) is a 160 MW onshore wind request withdrawn in the CAISO interconnection queue, in San Diego County, California, connecting to SDGE.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Apr 2014 (completed)
  2. Withdrawn / abandonedApr 2015 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
1060
Grid region
CAISO (California)
Utility / transmission owner
SDGE
Connection point (POI)
Boulevard East Substation 138kV
Location
San Diego County, California
Technology
Wind: 160 MW
Total requested
160 MW
Service type
Network resource (NRIS)
Study phase
System Impact Study
Queue status
Withdrawn
Entered queue
30 April 2014
Proposed online date
December 2017
Withdrawn
April 2015

Location

Marker shows the centre of San Diego County; the queue data does not give exact sites.

Power plants in California · Transmission lines in California

Other requests in San Diego County