United States โ€บ Grid โ€บ Interconnection queues

OCTARY USA ยท INTERCONNECTION QUEUES

Projects with signed interconnection agreements in the USA (2019 requests) โ€” page 3

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown34764.3 GW
Active in queue109.2 GW589 requests
Agreement signed64.3 GW347 requests
Withdrawn1,473226.5 GW never built

Map

Loading requestsโ€ฆ
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

347 requests ยท page 3 of 7
ProjectCapacityStatusLocationRegionQueuedOnline
Lynn Bark Energy Center
Solar
200 MWAgreement signed Martin, KYPJM Nov 2019target 2029
Solar project J1190, Clinton County
Solar
200 MWAgreement signed Clinton, IAMISO Jan 2019target 2025
Tanager Storage
Battery storage
200 MWAgreement signed Santa Clara, CACAISO Apr 2019target 2027
Solar project J1306, Perry County
Solar
200 MWAgreement signed Perry, ILMISO Apr 2019target 2024
Millers Branch Solar I
Solar ยท Miller's Branch Solar, LLC
200 MWAgreement signed Haskell, TXERCOT Dec 2019target 2025
Avocet Storage
Battery storage
200 MWAgreement signed Los Angeles, CACAISO Apr 2019target 2026
Rolling Farms Wind Project
Onshore wind
200 MWAgreement signed Christian, ILPJM Aug 2019target 2029
Armadillo Solar
Solar ยท Armadillo Solar Center, LLC
200 MWAgreement signed Navarro, TXERCOT Aug 2019target 2026
Lake Trout Solar
Solar + storage
200 MWAgreement signed Blackford, INPJM Sep 2019target 2028
Solar project J1381, Howard County
Solar
200 MWAgreement signed Howard, INMISO Apr 2019target 2026
Solar project J1348, Vermillion County
Solar
200 MWAgreement signed Vermillion, INMISO Apr 2019target 2025
Solar + storage project J1340, Jasper County
Solar + storage
200 MWAgreement signed Jasper, INMISO Apr 2019target 2025
Solar + storage project J1336, Jasper County
Solar + storage
200 MWAgreement signed Jasper, INMISO Apr 2019target 2025
Solar + storage project J1339, Jasper County
Solar + storage
200 MWAgreement signed Jasper, INMISO Apr 2019target 2025
CG Fulton County
Solar
199 MWAgreement signed Fulton, OHPJM Sep 2019target 2028
Onshore wind project J1292, Ionia County
Onshore wind
198 MWAgreement signed Ionia, MIMISO Apr 2019target 2024
Tres Bahias Solar
Solar ยท Tres Bahias Solar Power LLC
195 MWAgreement signed Calhoun, TXERCOT Mar 2019target 2025
Solar project 374, Lawrence County
Solar
195 MWAgreement signed Lawrence, TNSoutheast Jun 2019target 2028
Solar project 405, Lawrence County
Solar
193 MWAgreement signed Lawrence, ALSoutheast Nov 2019target 2027
Fleming Solar
Solar ยท AEUG Fleming Solar, LLC
189 MWAgreement signed Fleming, KYPJM Sep 2019target 2029
Nightfall Solar
Solar ยท BDPU SOLAR NIGHTFALL, LLC
181 MWAgreement signed Uvalde, TXERCOT May 2019target 2026
Hoosier Line Solar
Solar
180 MWAgreement signed White, INPJM Sep 2019target 2027
Sculpin Solar
Solar
180 MWAgreement signed Dekalb, INPJM Aug 2019target 2028
Water Valley Wind Energy
Onshore wind ยท Water Valley Wind Energy, LLC
180 MWAgreement signed Tom Green, TXERCOT Jan 2019target 2027
Sloopy Solar Energy Center
Solar
180 MWAgreement signed Clark, OHPJM Mar 2019target 2028
Solar project 387, Colbert County
Solar
178 MWAgreement signed Colbert, ALSoutheast Aug 2019target 2027
Solar project GEN-2019-039, Butler County
Solar
175 MWAgreement signed Butler, NESPP May 2019target 2027
Solar project 364, Logan County
Solar
173 MWAgreement signed Logan, KYSoutheast Apr 2019target 2024
Lamberton Road Battery
Battery storage
170 MWAgreement signed Mercer, NJPJM Sep 2019target 2027
Energy Storage
Battery storage
170 MWAgreement signed Norfolk, MAISO-NE Apr 2019target 2027
Lockhart Solar 2
Solar + storage
165 MWAgreement signed San Bernardino, CACAISO Apr 2019target 2026
Battery storage project J1355, Laporte County
Battery storage
160 MWAgreement signed Laporte, INMISO Apr 2019target 2026
Skycrest Solar Energy Center
Solar
155 MWAgreement signed Jay, INPJM Feb 2019target 2026
Springwater Solar
Solar
155 MWAgreement signed Madison, OHPJM Sep 2019target 2027
Solar project GEN-2019-045, Woods County
Solar
155 MWAgreement signed Woods, OKSPP May 2019target 2028
Eliza Solar
Solar ยท Ables Springs Solar, LLC
152 MWAgreement signed Kaufman, TXERCOT Jun 2019target 2025
Ulysses Solar
Solar ยท BNB Tennyson Solar LLC
151 MWAgreement signed Coke, TXERCOT Jan 2019target 2027
Onshore wind project MPC03900, Eddy County
Onshore wind
151 MWAgreement signed Eddy, NDMISO Apr 2019target 2027
Blackford Solar Energy Project
Solar
150 MWAgreement signed Jay, INPJM Sep 2019target 2026
Wild Grains Solar
Solar
150 MWAgreement signed Van Wert, OHPJM Oct 2019target 2027
Solar project J1482, White County
Solar
150 MWAgreement signed White, INMISO Apr 20192024
Solar project GEN-2019-003, Roosevelt County
Solar
150 MWAgreement signed Roosevelt, NMSPP Apr 2019target 2027
Solar project J1383, Fulton County
Solar
150 MWAgreement signed Fulton, ILMISO Apr 2019target 2025
Solar project J1465, Pointe Coupee Parish County
Solar
150 MWAgreement signed Pointe Coupee Parish, LAMISO Apr 2019target 2024
Solar project GEN-2019-055, Edwards County
Solar
150 MWAgreement signed Edwards, KSSPP May 2019target 2028
Solar project J1302, Saline County
Solar
150 MWAgreement signed Saline, ILMISO Apr 2019target 2025
Heritage Prairie Solar
Solar
150 MWAgreement signed Kankakee, ILPJM Mar 2019target 2027
Solar project J1382, Clark County
Solar
150 MWAgreement signed Clark, ILMISO Apr 2019target 2025
Battery storage project Q299, Maricopa County
Battery storage
150 MWAgreement signed Maricopa, AZWest Mar 2019target 2023
Solar project J1303, Jackson County
Solar
150 MWAgreement signed Jackson, ILMISO Apr 2019target 2026

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines ยท Planned power plants (EIA)