United States › Grid › Interconnection queues › Tennessee
SOLAR · SOUTHEASTSolar project 374, Lawrence County
Solar project 374, Lawrence County is a 195 MW solar request with a signed interconnection agreement in the Southeast interconnection queue, in Lawrence County, Tennessee, connecting to Tennessee Valley Authority.
Queue statusConsented
- PlanningQueued Jun 2019 (completed)
- Consented (current stage)
- Construction (not yet reached)
- OperatingTarget Jun 2028 (not yet reached)
- Closed (not yet reached)
Request details
- Queue ID
- 374
- Grid region
- Southeast (non-ISO utilities)
- Utility / transmission owner
- Tennessee Valley Authority
- Connection point (POI)
- Iron City, TN 161-kV Substation (future)
- Location
- Lawrence County, Tennessee
- Technology
- Solar: 195 MW
- Total requested
- 195 MW
- Study phase
- IA Executed
- Queue status
- Active
- Entered queue
- 4 June 2019
- Proposed online date
- June 2028
Location
Marker shows the centre of Lawrence County; the queue data does not give exact sites.
Other requests in Lawrence County
- Solar project 369, Lawrence CountySolar · 227 MW · withdrawn
- Solar project 582, Lawrence CountySolar · 195 MW · withdrawn
- Solar project 607, Lawrence CountySolar · 175 MW · withdrawn
- Solar project 367, Lawrence CountySolar · 160 MW · withdrawn
- Solar project 398, Lawrence CountySolar · 100 MW · withdrawn
- Solar project 462, Lawrence CountySolar · 80.0 MW · withdrawn
- Solar project 614, Lawrence CountySolar · 69.0 MW · withdrawn
- Solar project 616, Lawrence CountySolar · 66.0 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem