United States › Grid › Interconnection queues › California
OCTARY USA · INTERCONNECTION QUEUESWithdrawn queue requests in California — page 3
Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.
Map
Requests
| Project | Capacity | Status |
|---|---|---|
| Center Power Gas |
910 MW | Withdrawn / abandoned |
| Mira Loma Hybrid Power Project Gas |
910 MW | Withdrawn / abandoned |
| Viejo Hybrid Power Gas |
910 MW | Withdrawn / abandoned |
| Cadiz West Solar |
900 MW | Withdrawn / abandoned |
| Encina Generating Project (PH. 1 And 2) Gas |
900 MW | Withdrawn / abandoned |
| Yuha Desert Battery Storage 2 Battery storage |
900 MW | Withdrawn / abandoned |
| Wonder Solar Solar + storage |
892 MW | Withdrawn / abandoned |
| Three Rocks Solar + storage |
878 MW | Withdrawn / abandoned |
| Cosmos Battery storage |
874 MW | Withdrawn / abandoned |
| Magic Valley Wind 2 Wind + storage |
871 MW | Withdrawn / abandoned |
| K Road Calico Solar LLC (KRCS) (Fka Calico Solar 1; Ses Solar One) Solar |
850 MW | Withdrawn / abandoned |
| Gas project Q31, San Bernardino County Gas |
850 MW | Withdrawn / abandoned |
| Other project Q57, San Bernardino County Other |
850 MW | Withdrawn / abandoned |
| Clearwater Solar Generating Station Solar |
840 MW | Withdrawn / abandoned |
| Blue Star Energy Storage Battery storage |
829 MW | Withdrawn / abandoned |
| Brea Linda Energy Storage Battery storage |
829 MW | Withdrawn / abandoned |
| Brown Bear Energy Storage Battery storage |
829 MW | Withdrawn / abandoned |
| Solar Farm Energy Center Solar + storage |
822 MW | Withdrawn / abandoned |
| Hadselville Solar + storage |
816 MW | Withdrawn / abandoned |
| Estanislau Solar Storage Solar + storage |
816 MW | Withdrawn / abandoned |
| Yeager Mustang Solar + storage |
815 MW | Withdrawn / abandoned |
| Yeager Hybrid Solar Solar + storage |
813 MW | Withdrawn / abandoned |
| Longhorn 1 Solar + storage |
812 MW | Withdrawn / abandoned |
| Ibis Solar + storage |
811 MW | Withdrawn / abandoned |
| WSP 3 Solar |
800 MW | Withdrawn / abandoned |
| Ventura Clean Energy Gas |
778 MW | Withdrawn / abandoned |
| Muscat Battery storage |
772 MW | Withdrawn / abandoned |
| Central Coast Wind 1 Onshore wind |
772 MW | Withdrawn / abandoned |
| Trilobite Solar Project Solar |
750 MW | Withdrawn / abandoned |
| Palo Verde Mesa (Fka Brightsource Midpoint Solar) Solar |
750 MW | Withdrawn / abandoned |
| San Diego Community Power Generating Station Gas |
750 MW | Withdrawn / abandoned |
| California City Solar Solar |
732 MW | Withdrawn / abandoned |
| Fairfield Energy Center - 730 MW Gas |
730 MW | Withdrawn / abandoned |
| Gigantes Solar Solar |
730 MW | Withdrawn / abandoned |
| Bpae Kern Front Gas |
725 MW | Withdrawn / abandoned |
| Icarus Wind and Solar Solar + storage |
719 MW | Withdrawn / abandoned |
| Bradmoor Solar Solar + storage |
719 MW | Withdrawn / abandoned |
| Bright Star Hybrid Solar + storage |
719 MW | Withdrawn / abandoned |
| Sur Vista Solar + storage |
718 MW | Withdrawn / abandoned |
| Juglans Energy Storage Battery storage |
711 MW | Withdrawn / abandoned |
| Adastra Hybrid Solar Solar + storage |
709 MW | Withdrawn / abandoned |
| Mesaville Solar Solar + storage |
706 MW | Withdrawn / abandoned |
| Rock Dove 1 Energy Center Solar + storage |
701 MW | Withdrawn / abandoned |
| Rock Dove 2 Energy Center Solar + storage |
701 MW | Withdrawn / abandoned |
| Santa Ana Energy Center Gas |
700 MW | Withdrawn / abandoned |
| Blythe III Gas |
700 MW | Withdrawn / abandoned |
| PV-49 Solar |
700 MW | Withdrawn / abandoned |
| PV-47 Solar |
700 MW | Withdrawn / abandoned |
| PV-48 Solar |
700 MW | Withdrawn / abandoned |
| Desert Quartzsite PV Solar |
700 MW | Withdrawn / abandoned |
Capacity in the queue by state
Click a state to drill down.
By grid region
ISO/RTO markets and the non-ISO West and Southeast.
Requests by year joined
Capacity of requests in this view, by the year they entered the queue. Click a year.
Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)