SOLAR · CAISO

Desert Quartzsite PV

Desert Quartzsite PV is a 700 MW solar request withdrawn in the CAISO interconnection queue, in Riverside County, California, connecting to SCE.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Nov 2007 (completed)
  2. Withdrawn / abandonedDec 2009 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
270
Grid region
CAISO (California)
Utility / transmission owner
SCE
Connection point (POI)
Proposed Midpoint Substation 230kV
Location
Riverside County, California
Technology
Solar: 700 MW
Total requested
700 MW
Study phase
System Impact Study
Queue status
Withdrawn
Entered queue
1 November 2007
Proposed online date
December 2015
Withdrawn
December 2009

Location

Marker shows the centre of Riverside County; the queue data does not give exact sites.

Power plants in California · Transmission lines in California

Other requests in Riverside County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem