ONSHORE WIND · CAISO

Central Coast Wind 1

Central Coast Wind 1 is a 772 MW onshore wind request withdrawn in the CAISO interconnection queue, in Santa Barbara County, California, connecting to SCE.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Apr 2020 (completed)
  2. Withdrawn / abandonedJul 2020 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
1781
Grid region
CAISO (California)
Utility / transmission owner
SCE
Connection point (POI)
Goleta Substation 230kV
Location
Santa Barbara County, California
Technology
Wind: 772 MW
Total requested
772 MW
Service type
Network resource (NRIS)
Study phase
Feasibility Study
Queue status
Withdrawn
Entered queue
15 April 2020
Proposed online date
April 2027
Withdrawn
July 2020

Location

Marker shows the centre of Santa Barbara County; the queue data does not give exact sites.

Power plants in California · Transmission lines in California

Other requests in Santa Barbara County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem