United States › Grid › Interconnection queues
OCTARY USA · INTERCONNECTION QUEUESInterconnection queue in CAISO (California) — page 3
Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.
Map
Requests
| Project | Capacity | Status |
|---|---|---|
| Redonda Solar + storage |
542 MW | Agreement signed |
| Sagebrush Energy Storage Battery storage |
528 MW | In study |
| Daggett Solar 3 Solar + storage |
522 MW | Agreement signed |
| Summit Valley Energy Storage Battery storage |
519 MW | In study |
| Lupine Energy Center Battery storage |
518 MW | In study |
| Yellow Pine 3 Solar + storage |
517 MW | Agreement signed |
| Chronos Energy Storage Battery storage |
517 MW | In study |
| Alta Casa Storage Battery storage |
515 MW | Agreement signed |
| Yacht Rock Battery storage |
514 MW | In study |
| Dove Cove Battery storage |
514 MW | In study |
| Belterra Energy Storage Battery storage |
514 MW | In study |
| Fontus Battery storage |
514 MW | In study |
| Blue Star Solar + storage |
513 MW | In study |
| Greasewood Energy Storage Battery storage |
513 MW | Agreement signed |
| Cobalt Solar + storage |
513 MW | Agreement signed |
| Conduit Energy Storage Battery storage |
513 MW | Agreement signed |
| Rosa Storage Battery storage |
512 MW | In study |
| Bolt Solar + storage |
509 MW | In study |
| Lock Storage Battery storage |
508 MW | Agreement signed |
| Double Butte Storage Battery storage |
508 MW | Agreement signed |
| Torbino Solar Solar |
507 MW | In study |
| Galicia Storage Battery storage |
506 MW | In study |
| Ambar Energy Storage Battery storage |
505 MW | In study |
| Drifter Energy Storage Battery storage |
505 MW | Agreement signed |
| Ocotillo Express Wind + storage |
504 MW | Agreement signed |
| Spectrum Energy Storage Battery storage |
504 MW | Agreement signed |
| Delilah Energy Storage Battery storage |
504 MW | Agreement signed |
| Sterling Solar + storage |
500 MW | In study |
| Ironwood Solar Solar + storage |
500 MW | Agreement signed |
| Lake Elsinore Advanced Pumped Storage Project Battery storage |
500 MW | Agreement signed |
| Calvada Springs Solar Solar + storage |
500 MW | Agreement signed |
| Vulcan Solar + storage |
500 MW | In study |
| Goldback Solar Center Battery storage |
500 MW | Agreement signed |
| Hawkins Solar Hybrid Solar + storage |
500 MW | In study |
| Cantus Solar + storage |
499 MW | In study |
| Pluot Solar + storage |
479 MW | Agreement signed |
| Pomegranate Solar + storage |
479 MW | Agreement signed |
| Big SKY Solar Solar + storage |
476 MW | Agreement signed |
| Corby 2 Battery storage |
476 MW | In study |
| Shoals Energy Storage 2 Battery storage |
461 MW | In study |
| Mineral King Solar Solar + storage |
430 MW | In study |
| Boulder Brush Hybrid Wind + storage |
420 MW | In study |
| Tolenas Battery storage |
417 MW | In study |
| Alisa Solar Energy Complex Solar + storage |
417 MW | In study |
| Whiskey Diggings Solar |
414 MW | In study |
| Elysian Solar + storage |
412 MW | Agreement signed |
| Dos Palmas Battery storage |
411 MW | Agreement signed |
| Shoals Energy Storage Battery storage |
409 MW | Agreement signed |
| Solstice C Solar + storage |
408 MW | In study |
| Hidalgo Energy Storage Battery storage |
408 MW | Agreement signed |
Capacity in the queue by state
Click a state to drill down.
By grid region
ISO/RTO markets and the non-ISO West and Southeast.
- West (non-ISO utilities)1,857 · 519.1 GW
- ERCOT (Texas)1,986 · 447.3 GW
- MISO (Midcontinent)1,646 · 350.1 GW
- CAISO (California)429 · 188.6 GW
- Southeast (non-ISO utilities)1,067 · 161.4 GW
- SPP (Southwest Power Pool)692 · 152.4 GW
- PJM (Mid-Atlantic, Midwest)1,248 · 140.4 GW
- NYISO (New York)190 · 27.1 GW
- ISO-NE (New England)72 · 14.6 GW
Requests by year joined
Capacity of requests in this view, by the year they entered the queue. Click a year.
Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)