United States › Grid › Interconnection queues

OCTARY USA · INTERCONNECTION QUEUES

Withdrawn queue requests in the USA — page 268

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown24,2054,519.8 GW
Active in queue2,001.0 GW9,187 requests
Agreement signed423.2 GW2,141 requests
Withdrawn24,2054,519.8 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

24,205 requests · page 268 of 485
ProjectCapacityStatusLocationRegionQueuedOnline
Hydaspes
Solar + storage
82.0 MWWithdrawn / abandoned Stanislaus, CACAISO Apr 2018target 2022
Solar project IC-331, Terrell County
Solar
82.0 MWWithdrawn / abandoned Terrell, GASoutheast Jan 2014
Solar + storage project J3625, Winn Parish County
Solar + storage
82.0 MWWithdrawn / abandoned Winn Parish, LAMISO Apr 2024target 2027
Corpus Christi Upgrade
Gas · Calpine
82.0 MWWithdrawn / abandoned ERCOT Feb 2014target 2019
Battery storage project AH1-479, St. Joseph County
Battery storage
82.0 MWWithdrawn / abandoned St. Joseph, INPJM Sep 2021target 2023
Solar project J1023, Mississippi County
Solar
82.0 MWWithdrawn / abandoned Mississippi, ARMISO Mar 2018target 2021
Onshore wind project G0288, Pacific County
Onshore wind
82.0 MWWithdrawn / abandoned Pacific, WAWest Aug 2007target 2011
Onshore wind project 38, Wheatland County
Onshore wind
81.9 MWWithdrawn / abandoned Wheatland, MTWest Aug 2005target 2007
Solar project IC-571, Russell County
Solar
81.8 MWWithdrawn / abandoned Russell, ALSoutheast Dec 2016
Dos Amigos Solar
Solar
81.8 MWWithdrawn / abandoned Merced, CACAISO Apr 2015target 2020
Helix Storage
Battery storage
81.6 MWWithdrawn / abandoned San Diego, CACAISO Apr 2021target 2025
Solar project GEN-2021-SR1, Seminole County
Solar
81.6 MWWithdrawn / abandoned Seminole, OKSPP Feb 20212022
Solar project 123, Aiken County
Solar
81.6 MWWithdrawn / abandoned Aiken, SCSoutheast Feb 2019target 2021
SEGS10 Solar
Solar
81.4 MWWithdrawn / abandoned San Bernardino, CACAISO May 2016target 2019
Solar project AF2-363, Dekalb County
Solar
81.4 MWWithdrawn / abandoned Dekalb, ILPJM Mar 2020target 2020
Solar project AF2-364
Solar
81.4 MWWithdrawn / abandoned ILPJM Mar 2020target 2022
Bluegill Storage
Battery storage
81.4 MWWithdrawn / abandoned San Diego, CACAISO Apr 2020target 2025
Solemio
Solar · SOLEMIO LLC
81.4 MWWithdrawn / abandoned Hopkins, TXERCOT Jun 2017target 2023
Battery storage project AE2-338, Fayette County
Battery storage
81.2 MWWithdrawn / abandoned Fayette, KYPJM Mar 2019target 2022
Battery storage project AF2-213, York County
Battery storage
81.2 MWWithdrawn / abandoned York, PAPJM Mar 2020target 2022
Lunis Creek Storage 1
Battery storage · Lunis Creek Solar Project, LLC
81.2 MWWithdrawn / abandoned Jackson, TXERCOT May 2019target 2023
Onshore wind project GEN-2003-009, Carson County
Onshore wind
81.0 MWWithdrawn / abandoned Carson, TXSPP Jul 2003target 2004
Battery Storage
Battery storage
81.0 MWWithdrawn / abandoned Bristol, MAISO-NE Jun 2024target 2027
Onshore wind project GEN-2006-034, Sherman County
Onshore wind
81.0 MWWithdrawn / abandoned Sherman, KSSPP Aug 2006target 2008
Plaugher Ranch Solar
Solar + storage
81.0 MWWithdrawn / abandoned CACAISO Apr 2023target 2028
Onshore wind project H040, O'brien County
Onshore wind
81.0 MWWithdrawn / abandoned O'brien, IAMISO Jun 2008target 2010
Battery storage project 605, Mcnairy County
Battery storage
81.0 MWWithdrawn / abandoned Mcnairy, TNSoutheast Jan 2024
Onshore wind project GI-0616, Logan County
Onshore wind · Just Wind, LLC
81.0 MWWithdrawn / abandoned Logan, NDWest Oct 2006target 2011
Onshore wind project GEN-2012-005, Knox County
Onshore wind
81.0 MWWithdrawn / abandoned Knox, NESPP Mar 2012target 2015
Onshore wind project P53, Roanoke County
Onshore wind
81.0 MWWithdrawn / abandoned Roanoke, VAPJM Jan 2006target 2008
Western Ranch Solar1
Solar · Quantum Utility Generation
81.0 MWWithdrawn / abandoned ERCOT Apr 2009target 2050
Onshore wind project J088, Lenawee County
Onshore wind
81.0 MWWithdrawn / abandoned Lenawee, MIMISO Apr 2010target 2012
Battery Storage
Battery storage
80.9 MWWithdrawn / abandoned Middlesex, CTISO-NE May 2022target 2026
Onshore wind project IC-287, Etowah County
Onshore wind
80.5 MWWithdrawn / abandoned Etowah, ALSoutheast Mar 2013
Zircon BESS
Battery storage · Zircon BESS LLC
80.4 MWWithdrawn / abandoned La Salle, TXERCOT Jan 2025target 2028
Mica BESS
Battery storage · Mica BESS LLC
80.4 MWWithdrawn / abandoned Harris, TXERCOT Nov 2024target 2026
Solar project IC-671, Evans County
Solar
80.0 MWWithdrawn / abandoned Evans, GASoutheast Jan 2018
Solar project 570306, Franklin County
Solar · Masked
80.0 MWWithdrawn / abandoned Franklin, NCSoutheast Jun 2022
Solar + storage project IC-1093, Lowndes County
Solar + storage
80.0 MWWithdrawn / abandoned Lowndes, ALSoutheast Nov 2022
Echelon Solar
Solar + storage · Echelon Solar LLC
80.0 MWWithdrawn / abandoned Carroll, OHPJM Sep 2021target 2025
Solar project J2562, Arkansas County
Solar
80.0 MWWithdrawn / abandoned Arkansas, ARMISO Sep 2022target 2025
Solar project 85, Pima County
Solar
80.0 MWWithdrawn / abandoned Pima, AZWest Dec 2020target 2023
Solar project 683, Beaver County
Solar
80.0 MWWithdrawn / abandoned Beaver, UTWest Jul 2015target 2016
Solar project AH1-339, Wyandot County
Solar · River Otter Solar LLC
80.0 MWWithdrawn / abandoned Wyandot, OHPJM Feb 2025target 2025
Onshore wind project G366, Columbia County
Onshore wind
80.0 MWWithdrawn / abandoned Columbia, WIMISO Oct 2003target 2005
Solar project G0563, Yakima County
Solar
80.0 MWWithdrawn / abandoned Yakima, WAWest May 2017target 2019
Solar project AF2-164, Venango County
Solar · Heartland Solar LLC
80.0 MWWithdrawn / abandoned Venango, PAPJM Mar 2020target 2023
Solar project 587, Emery County
Solar
80.0 MWWithdrawn / abandoned Emery, UTWest Jul 2014target 2016
Solar project GI-89, Scott County
Solar
80.0 MWWithdrawn / abandoned Scott, MOSoutheast Jan 2020target 2022
Solar project AA1-064, Northampton County
Solar
80.0 MWWithdrawn / abandoned Northampton, NCPJM Sep 2014target 2015
Page 268 of 485

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)