United States βΊ Grid βΊ Interconnection queues βΊ Illinois
SOLAR Β· PJMSolar project AF2-364
Solar project AF2-364 is a 81.4 MW solar request withdrawn in the PJM interconnection queue, connecting to ComEd.
Queue statusWithdrawn / abandoned
- PlanningQueued Mar 2020 (completed)
- Withdrawn / abandonedApr 2021 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- AF2-364
- Grid region
- PJM (Mid-Atlantic, Midwest)
- Utility / transmission owner
- ComEd
- Connection point (POI)
- Wayne Red 138 kV
- Location
- Illinois
- Technology
- Solar: 81.4 MW
- Total requested
- 81.4 MW
- Service type
- Network resource (NRIS)
- Study phase
- Available studies: Feasibility Study, System Impact Study
- Queue status
- Withdrawn
- Entered queue
- 31 March 2020
- Proposed online date
- December 2022
- Withdrawn
- April 2021
Location
No county location in the queue data.
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem