United States β€Ί Grid β€Ί Interconnection queues β€Ί Ohio

SOLAR + STORAGE Β· PJM

Echelon Solar

Echelon Solar is a 80.0 MW solar + storage request withdrawn in the PJM interconnection queue, in Carroll County, Ohio, connecting to ATSI.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Sep 2021 (completed)
  2. Withdrawn / abandonedJun 2025 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
AH1-526
Grid region
PJM (Mid-Atlantic, Midwest)
Utility / transmission owner
ATSI
Developer
Echelon Solar LLC
Connection point (POI)
Knox - Washington CEC 138 kV
Location
Carroll County, Ohio
Technology
Solar: 80.0 MW Β· Battery
Total requested
80.0 MW
Service type
Network resource (NRIS)
Study phase
In Progress (unknown study)
Queue status
Withdrawn
Entered queue
11 September 2021
Proposed online date
October 2025
Withdrawn
June 2025

Location

Marker shows the centre of Carroll County; the queue data does not give exact sites.

Power plants in Ohio Β· Transmission lines in Ohio

Other requests in Carroll County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem