United States βΊ Grid βΊ Interconnection queues βΊ Ohio
SOLAR + STORAGE Β· PJMEchelon Solar
Echelon Solar is a 80.0 MW solar + storage request withdrawn in the PJM interconnection queue, in Carroll County, Ohio, connecting to ATSI.
Queue statusWithdrawn / abandoned
- PlanningQueued Sep 2021 (completed)
- Withdrawn / abandonedJun 2025 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- AH1-526
- Grid region
- PJM (Mid-Atlantic, Midwest)
- Utility / transmission owner
- ATSI
- Developer
- Echelon Solar LLC
- Connection point (POI)
- Knox - Washington CEC 138 kV
- Location
- Carroll County, Ohio
- Technology
- Solar: 80.0 MW Β· Battery
- Total requested
- 80.0 MW
- Service type
- Network resource (NRIS)
- Study phase
- In Progress (unknown study)
- Queue status
- Withdrawn
- Entered queue
- 11 September 2021
- Proposed online date
- October 2025
- Withdrawn
- June 2025
Location
Marker shows the centre of Carroll County; the queue data does not give exact sites.
Other requests in Carroll County
- Gas project AH1-680, Carroll CountyGas Β· 1,300 MW Β· in study
- Carroll County Energy LLCGas Β· 742 MW Β· built
- Carroll County Energy LLCGas Β· 20.0 MW Β· built
- Gas project Y2-085, Carroll CountyGas Β· 1,050 MW Β· withdrawn
- Solar project AH2-275, Carroll CountySolar Β· 100 MW Β· withdrawn
- Solar project AH1-551, Carroll CountySolar Β· 100 MW Β· withdrawn
- Solar project AH1-236, Carroll CountySolar Β· 8.0 MW Β· withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem