Onshore wind project GEN-2006-034, Sherman County

Onshore wind project GEN-2006-034, Sherman County is a 81.0 MW onshore wind request withdrawn in the SPP interconnection queue, in Sherman County, Kansas, connecting to SUNC.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Aug 2006 (completed)
  2. Withdrawn / abandoned (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
GEN-2006-034
Grid region
SPP (Southwest Power Pool)
Utility / transmission owner
SUNC
Connection point (POI)
Kanarado 115kV
Location
Sherman County, Kansas
Technology
Wind: 81.0 MW
Total requested
81.0 MW
Service type
Energy only (ERIS)
Study phase
WITHDRAWN
Queue status
Withdrawn
Entered queue
23 August 2006
Proposed online date
August 2008

Location

Marker shows the centre of Sherman County; the queue data does not give exact sites.

Power plants in Kansas Β· Transmission lines in Kansas

Other requests in Sherman County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem