United States βΊ Grid βΊ Interconnection queues βΊ Kansas
ONSHORE WIND Β· WESTOnshore wind project GI-TC-2024-27, Sherman County
Onshore wind project GI-TC-2024-27, Sherman County is a 298 MW onshore wind request withdrawn in the West interconnection queue, in Sherman County, Kansas, connecting to Tri-State Generation and Transmission Association.
Queue statusWithdrawn / abandoned
- PlanningQueued May 2023 (completed)
- Withdrawn / abandoned (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- GI-TC-2024-27
- Grid region
- West (non-ISO utilities)
- Utility / transmission owner
- Tri-State Generation and Transmission Association
- Connection point (POI)
- Burlington 230 kV Substation
- Location
- Sherman County, Kansas
- Technology
- Wind: 298 MW
- Total requested
- 298 MW
- Service type
- Network resource (NRIS)
- Queue status
- Withdrawn
- Entered queue
- 30 May 2023
- Proposed online date
- December 2028
Location
Marker shows the centre of Sherman County; the queue data does not give exact sites.
Other requests in Sherman County
- Onshore wind project GEN-2021-045, Sherman CountyOnshore wind Β· 300 MW Β· withdrawn
- Onshore wind project GEN-2008-025, Sherman CountyOnshore wind Β· 101 MW Β· withdrawn
- Onshore wind project GEN-2006-034, Sherman CountyOnshore wind Β· 81.0 MW Β· withdrawn
- Coal project GEN-2007-003, Sherman CountyCoal Β· 30.0 MW Β· withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem