United States › Grid › Interconnection queues

OCTARY USA · INTERCONNECTION QUEUES

Withdrawn queue requests in the USA — page 259

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown24,2054,519.8 GW
Active in queue2,001.0 GW9,187 requests
Agreement signed423.2 GW2,141 requests
Withdrawn24,2054,519.8 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

24,205 requests · page 259 of 485
ProjectCapacityStatusLocationRegionQueuedOnline
Onshore wind project GI-0614, Mountrail County
Onshore wind · AltaGas Renewable
99.0 MWWithdrawn / abandoned Mountrail, NDWest Aug 2006target 2008
Onshore wind project J044, Edgar County
Onshore wind
99.0 MWWithdrawn / abandoned Edgar, ILMISO May 2009target 2012
Onshore wind project 2007-G5
Onshore wind
99.0 MWWithdrawn / abandoned West Jun 2007target 2013
Onshore wind project J198, Lyon County
Onshore wind
99.0 MWWithdrawn / abandoned Lyon, MNMISO Feb 2011target 2012
Onshore wind project 2008-G12
Onshore wind
99.0 MWWithdrawn / abandoned West Jul 2008target 2011
Onshore wind project 182, Natrona County
Onshore wind · PacifiCorp Commercial & Trading
99.0 MWWithdrawn / abandoned Natrona, WYWest Jan 2008target 2011
Ramco Energy Center
Gas
99.0 MWWithdrawn / abandoned San Diego, CACAISO Jun 2007target 2010
Onshore wind project 125, Converse County
Onshore wind
99.0 MWWithdrawn / abandoned Converse, WYWest Mar 2007target 2008
Onshore wind project GEN-2002-017, Dewey County
Onshore wind
99.0 MWWithdrawn / abandoned Dewey, OKSPP Aug 2002
Other project G013, Manitowoc County
Other
99.0 MWWithdrawn / abandoned Manitowoc, WIMISO Oct 1999target 2003
Onshore wind project G611, Calumet County
Onshore wind
99.0 MWWithdrawn / abandoned Calumet, WIMISO Mar 2006target 2006
Onshore wind project J1512, Lafayette County
Onshore wind
98.9 MWWithdrawn / abandoned Lafayette, WIMISO Jun 2020target 2023
Montezuma II Expansion
Onshore wind
98.9 MWWithdrawn / abandoned Solano, CACAISO Jul 2009target 2014
Solar project J2169, Beauregard Parish County
Solar
98.9 MWWithdrawn / abandoned Beauregard Parish, LAMISO Aug 2021target 2023
Onshore wind project 441, Umatilla County
Onshore wind
98.9 MWWithdrawn / abandoned Umatilla, ORWest Oct 2012target 2016
Onshore wind project 276, Walla Walla County
Onshore wind
98.9 MWWithdrawn / abandoned Walla Walla, WAWest Jun 2009target 2020
Solar project GI-82, Payne County
Solar
98.8 MWWithdrawn / abandoned Payne, OKSoutheast May 2019target 2022
Olympus Power
Gas
98.8 MWWithdrawn / abandoned San Diego, CACAISO May 2007target 2010
Lonestar
Gas
98.8 MWWithdrawn / abandoned San Diego, CACAISO May 2007target 2010
Oceanside
Gas
98.8 MWWithdrawn / abandoned San Diego, CACAISO May 2007target 2010
Stevinson
Solar + storage
98.8 MWWithdrawn / abandoned Merced, CACAISO Apr 2019target 2023
Onshore wind project 142, Uinta County
Onshore wind · Bridger Butte Power, LLC
98.7 MWWithdrawn / abandoned Uinta, WYWest Jun 2007target 2009
Onshore wind project GEN-2023-012, Kingsbury County
Onshore wind
98.6 MWWithdrawn / abandoned Kingsbury, SDSPP Oct 2023target 2026
Onshore wind project 411, Umatilla County
Onshore wind
98.4 MWWithdrawn / abandoned Umatilla, ORWest Feb 2012
Onshore wind project J2115, Macon County
Onshore wind
98.3 MWWithdrawn / abandoned Macon, ILMISO Aug 2021target 2024
Karankawa 2 Expansion
Onshore wind · Karankawa Wind, LLC
98.3 MWWithdrawn / abandoned San Patricio, TXERCOT May 2019target 2022
Solar project IC-481, Macon County
Solar
98.1 MWWithdrawn / abandoned Macon, GASoutheast Aug 2016
Llano Estacado Energy Storage
Other · VESI 40 LLC
98.0 MWWithdrawn / abandoned Howard, TXERCOT Apr 2022target 2025
Solar
Solar
98.0 MWWithdrawn / abandoned Cheshire, NHISO-NE Jan 2016target 2018
Onshore wind project 185, Albany County
Onshore wind · PacifiCorp Commercial & Trading
98.0 MWWithdrawn / abandoned Albany, WYWest Jan 2008target 2009
Onshore wind project 180, Natrona County
Onshore wind · PacifiCorp Commercial & Trading
98.0 MWWithdrawn / abandoned Natrona, WYWest Jan 2008target 2010
Penn Forest Wind Project
Onshore wind
98.0 MWWithdrawn / abandoned Carbon, PAPJM Nov 2014target 2020
Onshore wind project G427, Fond Du Lac County
Onshore wind
98.0 MWWithdrawn / abandoned Fond Du Lac, WIMISO May 2004target 2004
Solar project AG1-353, Taylor County
Solar · Creekview Solar, LLC
98.0 MWWithdrawn / abandoned Taylor, KYPJM Sep 2020target 2023
Onshore wind project J637, Deuel County
Onshore wind
98.0 MWWithdrawn / abandoned Deuel, SDMISO May 2016target 2018
Solar project AF2-263, Shelby County
Solar · AEUG Shelby Solar, LLC
98.0 MWWithdrawn / abandoned Shelby, OHPJM Mar 2020target 2022
Gas project GEN-2023-062, Williams County
Gas
98.0 MWWithdrawn / abandoned Williams, NDSPP Oct 2023target 2028
Solar project AH1-485, Wayne County
Solar
98.0 MWWithdrawn / abandoned Wayne, OHPJM Sep 2021target 2023
Solar project IC-487, Baldwin County
Solar
98.0 MWWithdrawn / abandoned Baldwin, ALSoutheast Aug 2016
RE Palmwood 1 Solar
Solar · Recurrent Energy
98.0 MWWithdrawn / abandoned ERCOT Sep 2014target 2017
Onshore wind project G590, Calumet County
Onshore wind
98.0 MWWithdrawn / abandoned Calumet, WIMISO Jan 2006target 2007
Onshore wind project 183, Natrona County
Onshore wind · PacifiCorp Commercial & Trading
98.0 MWWithdrawn / abandoned Natrona, WYWest Jan 2008target 2012
Onshore wind project J165, Fulton County
Onshore wind
97.6 MWWithdrawn / abandoned Fulton, OHMISO Sep 2010target 2012
Onshore wind project W3-059B_AT7, Fulton County
Onshore wind
97.6 MWWithdrawn / abandoned Fulton, OHPJM Sep 2010target 2010
Solar project J2231, Jefferson County
Solar
97.5 MWWithdrawn / abandoned Jefferson, ARMISO Aug 2021target 2024
Onshore wind project Y3-035, Marshall County
Onshore wind
97.5 MWWithdrawn / abandoned Marshall, ILPJM Feb 2013target 2015
Onshore wind project J177, St. Croix County
Onshore wind
97.5 MWWithdrawn / abandoned St. Croix, WIMISO Nov 2010target 2015
Onshore wind project AE1-233, Dekalb County
Onshore wind
97.5 MWWithdrawn / abandoned Dekalb, ILPJM Sep 2018target 2021
Peabody Power
Gas
97.2 MWWithdrawn / abandoned Essex, MAISO-NE Feb 2003target 2008
Henrietta II
Gas
97.2 MWWithdrawn / abandoned Kings, CACAISO Mar 2005target 2008
Page 259 of 485

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)