United States › Grid › Interconnection queues › Texas
ONSHORE WIND · ERCOTKarankawa 2 Expansion
Karankawa 2 Expansion is a 98.3 MW onshore wind request withdrawn in the ERCOT interconnection queue, in San Patricio County, Texas.
Queue statusWithdrawn / abandoned
- PlanningQueued May 2019 (completed)
- Withdrawn / abandonedSep 2020 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- 20INR0265
- Grid region
- ERCOT (Texas)
- Developer
- Karankawa Wind, LLC
- Connection point (POI)
- tap 345kV 8455 Lon Hill - 5725 Pawnee, new sub Goddard
- Location
- San Patricio County, Texas
- Technology
- Wind: 98.3 MW
- Total requested
- 98.3 MW
- Study phase
- FIS Complete
- Queue status
- Withdrawn
- Entered queue
- 12 May 2019
- Proposed online date
- December 2022
- Withdrawn
- September 2020
Location
Marker shows the centre of San Patricio County; the queue data does not give exact sites.
Other requests in San Patricio County
- SanPat Solar ISolar · 309 MW · agreement signed
- Alila SolarSolar + storage · 257 MW · agreement signed
- SanPat Solar IISolar · 256 MW · agreement signed
- Pintail Pass BESSBattery storage · 207 MW · agreement signed
- Jackalope SolarSolar · 156 MW · agreement signed
- Bowstring BESSBattery storage · 155 MW · agreement signed
- Hecate Energy Arkansas WindOnshore wind · 1,029 MW · in study
- Gregory Power Development SLFGas · 470 MW · in study
- Titus Low Carbon Ventures Solar 1Solar · 338 MW · in study
- Sunburst SolarSolar + storage · 302 MW · in study
- Gulf Gateway Storage OneSolar + storage · 301 MW · in study
- Gulf Gateway Solar OneSolar + storage · 301 MW · in study
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem