United States βΊ Grid βΊ Interconnection queues βΊ Oregon
ONSHORE WIND Β· WESTOnshore wind project 411, Umatilla County
Onshore wind project 411, Umatilla County is a 98.4 MW onshore wind request withdrawn in the West interconnection queue, in Umatilla County, Oregon, connecting to PacifiCorp.
Queue statusWithdrawn / abandoned
- PlanningQueued Feb 2012 (completed)
- Withdrawn / abandonedMar 2017 (project stopped here)
- ConsentedApr 2013 (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- 411
- Grid region
- West (non-ISO utilities)
- Utility / transmission owner
- PacifiCorp
- Connection point (POI)
- Pendleton-Weston Line
- Location
- Umatilla County, Oregon
- Technology
- Wind: 98.4 MW
- Total requested
- 98.4 MW
- Service type
- Energy only (ERIS)
- Study phase
- IA signed 4/22/13, Suspended 3/1/2014, Terminated 3/3/17
- Queue status
- Withdrawn
- Entered queue
- 16 February 2012
- Agreement signed
- 22 April 2013
- Withdrawn
- March 2017
Location
Marker shows the centre of Umatilla County; the queue data does not give exact sites.
Other requests in Umatilla County
- Solar + storage project C2-175, Umatilla CountySolar + storage Β· 80.0 MW Β· agreement signed
- Solar + storage project G0777, Umatilla CountySolar + storage Β· 1,300 MW Β· in study
- Battery storage project G0778, Umatilla CountyBattery storage Β· 650 MW Β· in study
- Battery storage project G0965, Umatilla CountyBattery storage Β· 650 MW Β· in study
- Other project G0854, Umatilla CountyOther Β· 600 MW Β· in study
- Solar + storage project G0908, Umatilla CountySolar + storage Β· 500 MW Β· in study
- Onshore wind project G1013, Umatilla CountyOnshore wind Β· 250 MW Β· in study
- Solar + storage project G1062, Umatilla CountySolar + storage Β· 205 MW Β· in study
- Solar + storage project G1063, Umatilla CountySolar + storage Β· 175 MW Β· in study
- Solar + storage project G0738, Umatilla CountySolar + storage Β· 85.0 MW Β· in study
- Solar + storage project PIS104, Umatilla CountySolar + storage Β· 80.0 MW Β· in study
- Onshore wind project G1012, Umatilla CountyOnshore wind Β· 67.0 MW Β· in study
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem