Withdrawn queue requests in MISO (Midcontinent) — page 25

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown3,261621.9 GW
Active in queue350.1 GW1,646 requests
Agreement signed28.1 GW187 requests
Withdrawn3,261621.9 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

3,261 requests · page 25 of 66
ProjectCapacityStatusLocationRegionQueuedOnline
Solar + storage project J3606, Cross County
Solar + storage
198 MWWithdrawn / abandoned Cross, ARMISO Apr 2024target 2028
Solar project J3855, Madison County
Solar
198 MWWithdrawn / abandoned Madison, MSMISO Dec 2024target 2028
Solar project J1771, Cumberland County
Solar
197 MWWithdrawn / abandoned Cumberland, ILMISO Jun 2020target 2023
Battery storage project J2652, Dakota County
Battery storage
197 MWWithdrawn / abandoned Dakota, MNMISO Sep 2022target 2026
Solar project J3969, Poinsett County
Solar
196 MWWithdrawn / abandoned Poinsett, ARMISO Mar 2025target 2030
Gas project J2144, Jasper County
Gas
195 MWWithdrawn / abandoned Jasper, INMISO Sep 2021target 2024
Solar project J2813, Saginaw County
Solar
195 MWWithdrawn / abandoned Saginaw, MIMISO Sep 2022target 2027
Solar project J1551, Morehouse Parish County
Solar
195 MWWithdrawn / abandoned Morehouse Parish, LAMISO Jun 2020target 2024
Gas project J073, Blue Earth County
Gas
194 MWWithdrawn / abandoned Blue Earth, MNMISO Oct 2010target 2012
Onshore wind project J3206, Cerro Gordo County
Onshore wind
194 MWWithdrawn / abandoned Cerro Gordo, IAMISO Sep 2022target 2027
Solar project J1668, Iberville Parish County
Solar
194 MWWithdrawn / abandoned Iberville Parish, LAMISO Jun 2020target 2023
Gas project G267, Mcleod County
Gas
190 MWWithdrawn / abandoned Mcleod, MNMISO Nov 2002target 2007
Solar project J2018, Clark County
Solar
190 MWWithdrawn / abandoned Clark, WIMISO Nov 2021target 2026
Onshore wind project J897, Grand Forks County
Onshore wind
190 MWWithdrawn / abandoned Grand Forks, NDMISO Jun 2017target 2024
Solar project J3257, Pulaski County
Solar
190 MWWithdrawn / abandoned Pulaski, INMISO Apr 2024target 2026
Battery storage project J2766, Howard County
Battery storage
190 MWWithdrawn / abandoned Howard, INMISO Aug 2023target 2025
Solar + storage project J3536, Poinsett County
Solar + storage
190 MWWithdrawn / abandoned Poinsett, ARMISO Apr 2024target 2028
Onshore wind project J1961, Cass County
Onshore wind
190 MWWithdrawn / abandoned Cass, NDMISO Aug 2021target 2026
Gas project J561, Kalamazoo County
Gas
190 MWWithdrawn / abandoned Kalamazoo, MIMISO May 2016target 2017
Solar + storage project J3680, Scott County
Solar + storage
189 MWWithdrawn / abandoned Scott, MSMISO Apr 2024target 2028
Gas project G268, Wood County
Gas
189 MWWithdrawn / abandoned Wood, WIMISO Nov 2002target 2005
Solar project J3025, Douglas County
Solar
188 MWWithdrawn / abandoned Douglas, MNMISO Sep 2022target 2027
Solar project J3462, Tama County
Solar
187 MWWithdrawn / abandoned Tama, IAMISO Apr 2024target 2028
Onshore wind project J156, Marshall County
Onshore wind
186 MWWithdrawn / abandoned Marshall, INMISO Jun 2010
Onshore wind project J2546, Deuel County
Onshore wind
185 MWWithdrawn / abandoned Deuel, SDMISO Sep 2022target 2027
Solar + storage project J3214, Lee County
Solar + storage
185 MWWithdrawn / abandoned Lee, IAMISO Sep 2022target 2024
Replacing 179 MW Coal with 179 MW Solar; Edwards Unit 3
Other
185 MWWithdrawn / abandoned Tazewell, ILMISO Jul 2024target 2025
Solar project J2493, Arenac County
Solar
184 MWWithdrawn / abandoned Arenac, MIMISO Sep 2022target 2025
Onshore wind project H010, Madison County
Onshore wind
182 MWWithdrawn / abandoned Madison, IAMISO Apr 2008target 2010
Solar project J3174, Scott County
Solar
180 MWWithdrawn / abandoned Scott, ILMISO Sep 2022target 2026
Solar project J3308, Woodruff County
Solar
180 MWWithdrawn / abandoned Woodruff, ARMISO Apr 2024target 2027
Solar + storage project J3019, East Feliciana Parish County
Solar + storage
180 MWWithdrawn / abandoned East Feliciana Parish, LAMISO Sep 2022target 2027
Solar project J2130, Vermillion County
Solar
180 MWWithdrawn / abandoned Vermillion, INMISO Mar 2022target 2024
Onshore wind project G221, Dickey County
Onshore wind
180 MWWithdrawn / abandoned Dickey, NDMISO Apr 2002target 2005
Solar + storage project J3108, Jasper County
Solar + storage
180 MWWithdrawn / abandoned Jasper, MSMISO Sep 2022target 2026
Solar project J1815, Montgomery County
Solar
180 MWWithdrawn / abandoned Montgomery, INMISO Mar 2022target 2023
Solar project J1829, Shelby County
Solar
180 MWWithdrawn / abandoned Shelby, INMISO Jun 2020target 2024
Battery storage project J3614, Ashley County
Battery storage
180 MWWithdrawn / abandoned Ashley, ARMISO Apr 2024target 2028
Solar + storage project J2321, Lamar County
Solar + storage
180 MWWithdrawn / abandoned Lamar, MSMISO May 2022target 2025
Battery storage project J4067, Panola County
Battery storage
180 MWWithdrawn / abandoned Panola, MSMISO Sep 2025target 2029
Replacing 180MW with BESS of the existing 280 MW Steam; LANSING 4
Other
180 MWWithdrawn / abandoned Allamakee, IAMISO Sep 2023target 2026
Onshore wind project J899, Carroll County
Onshore wind
180 MWWithdrawn / abandoned Carroll, ARMISO Jun 2017target 2019
Solar project J3301, Prairie County
Solar
180 MWWithdrawn / abandoned Prairie, ARMISO Apr 2024target 2027
Onshore wind project H032, Polk County
Onshore wind
180 MWWithdrawn / abandoned Polk, MNMISO May 2008target 2012
Onshore wind project J1952, Cerro Gordo County
Onshore wind
180 MWWithdrawn / abandoned Cerro Gordo, IAMISO Aug 2021target 2024
Solar project J1995, Richland Parish County
Solar
180 MWWithdrawn / abandoned Richland Parish, LAMISO Aug 2021target 2025
Solar project J2096, Terrebonne Parish County
Solar
180 MWWithdrawn / abandoned Terrebonne Parish, LAMISO Aug 2021target 2024
Solar project J3613, Ashley County
Solar
180 MWWithdrawn / abandoned Ashley, ARMISO Apr 2024target 2028
Solar project J2385, Franklin Parish County
Solar
179 MWWithdrawn / abandoned Franklin Parish, LAMISO Sep 2022target 2027
Solar project J2494, Midland County
Solar
178 MWWithdrawn / abandoned Midland, MIMISO Sep 2022target 2025
Page 25 of 66

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)