πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues β€Ί Michigan

SOLAR Β· MISO

Solar project J2813, Saginaw County

Solar project J2813, Saginaw County is a 195 MW solar request withdrawn in the MISO interconnection queue, in Saginaw County, Michigan, connecting to METC.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Sep 2022 (completed)
  2. Withdrawn / abandonedMar 2023 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
J2813
Grid region
MISO (Midcontinent)
Utility / transmission owner
METC
Connection point (POI)
Slate Goss 345 KV Line
Location
Saginaw County, Michigan
Technology
Solar: 195 MW
Total requested
195 MW
Service type
Network resource (NRIS)
Study phase
Study Phase: DPP 2; Post GIA Status: Not Started
Queue status
Withdrawn
Entered queue
13 September 2022
Proposed online date
February 2027
Withdrawn
March 2023

Location

Marker shows the centre of Saginaw County; the queue data does not give exact sites.

Power plants in Michigan Β· Transmission lines in Michigan

Other requests in Saginaw County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem