Replacing 180MW with BESS of the existing 280 MW Steam; LANSING 4

Replacing 180MW with BESS of the existing 280 MW Steam; LANSING 4 is a 180 MW other request withdrawn in the MISO interconnection queue, in Allamakee County, Iowa, connecting to ITC MIDWEST.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Sep 2023 (completed)
  2. Withdrawn / abandoned (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
R1037
Grid region
MISO (Midcontinent)
Utility / transmission owner
ITC MIDWEST
Connection point (POI)
ITCM Lansing 161kV
Location
Allamakee County, Iowa
Technology
Other: 180 MW · Battery
Total requested
180 MW
Service type
Network resource (NRIS)
Queue status
Withdrawn
Entered queue
28 September 2023
Proposed online date
February 2026

Location

Marker shows the centre of Allamakee County; the queue data does not give exact sites.

Power plants in Iowa · Transmission lines in Iowa

Other requests in Allamakee County