United States βΊ Grid βΊ Interconnection queues βΊ Iowa
BATTERY STORAGE Β· MISOBattery storage project J1733, Allamakee County
Battery storage project J1733, Allamakee County is a 50.0 MW battery storage request withdrawn in the MISO interconnection queue, in Allamakee County, Iowa, connecting to ITC MIDWEST.
Queue statusWithdrawn / abandoned
- PlanningQueued Jun 2020 (completed)
- Withdrawn / abandoned (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- J1733
- Grid region
- MISO (Midcontinent)
- Utility / transmission owner
- ITC MIDWEST
- Connection point (POI)
- Lansing 161 kV
- Location
- Allamakee County, Iowa
- Technology
- Battery: 50.0 MW
- Total requested
- 50.0 MW
- Service type
- Network resource (NRIS)
- Study phase
- Study Phase: GIA In Process; Post GIA Status: Not Started
- Queue status
- Withdrawn
- Entered queue
- 24 June 2020
- Proposed online date
- June 2025
Location
Marker shows the centre of Allamakee County; the queue data does not give exact sites.
Other requests in Allamakee County
- Replacing 150 MW of coal generation with BESS at Lansing; Lansing 4Battery storage Β· 150 MW Β· in study
- Replacing 130 MW of coal generation with BESS at Lansing; Lansing 4Battery storage Β· 130 MW Β· in study
- Replacing 100 MW of existing coal generation with 28 Power Electronic 4.01 MVA at Lansing Generation Station; Lansing 4Other Β· 280 MW Β· withdrawn
- Onshore wind project G869, Allamakee CountyOnshore wind Β· 200 MW Β· withdrawn
- Replacing 180MW with BESS of the existing 280 MW Steam; LANSING 4Other Β· 180 MW Β· withdrawn
- Onshore wind project J3527, Allamakee CountyOnshore wind Β· 136 MW Β· withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem