| Project | Capacity | Status |
|---|---|---|
| Solar + storage project Q440, La Paz County Solar + storage |
95.0 MW | Withdrawn / abandoned |
| Solar project AG2-168, Russell County Solar |
95.0 MW | Withdrawn / abandoned |
| Solar project J2025, St. James Parish County Solar |
95.0 MW | Withdrawn / abandoned |
| Solar project J2023, Amite County Solar |
94.1 MW | Withdrawn / abandoned |
| Solar + storage project AG2-604, Montgomery County Solar + storage |
94.0 MW | Withdrawn / abandoned |
| Gas project GEN-2021-093, Oklahoma County Gas |
93.0 MW | Withdrawn / abandoned |
| Solar project AH1-350, Stark County Solar |
92.4 MW | Withdrawn / abandoned |
| Calloway BESS Battery storage |
92.1 MW | Withdrawn / abandoned |
| Solar + storage project J2073, Ohio County Solar + storage |
91.5 MW | Withdrawn / abandoned |
| Sweetbrier Hybrid Solar Solar + storage |
90.8 MW | Withdrawn / abandoned |
| Battery storage project AH1-606, Union County Battery storage |
90.0 MW | Withdrawn / abandoned |
| Battery storage project AH1-043, Middlesex County Battery storage |
90.0 MW | Withdrawn / abandoned |
| Solar + storage project AG2-584, Frederick County Solar + storage |
90.0 MW | Withdrawn / abandoned |
| Solar project J2286, Polk County Solar |
90.0 MW | Withdrawn / abandoned |
| Solar + storage project AG2-666, Jackson County Solar + storage |
90.0 MW | Withdrawn / abandoned |
| Battery storage project AG2-224, Essex County Battery storage |
90.0 MW | Withdrawn / abandoned |
| Battery storage project J2015, Tunica County Battery storage |
90.0 MW | Withdrawn / abandoned |
| Solar + storage project AH1-092, Halifax County Solar + storage ยท Scarlet Oak Solar, LLC |
90.0 MW | Withdrawn / abandoned |
| Solar project AH1-429, Fleming County Solar ยท ACE Development Company, LLC |
90.0 MW | Withdrawn / abandoned |
| Solar project J1957, Coahoma County Solar |
90.0 MW | Withdrawn / abandoned |
| Battery storage project Q411, Maricopa County Battery storage |
90.0 MW | Withdrawn / abandoned |
| Battery storage project J1964, Columbia County Battery storage |
90.0 MW | Withdrawn / abandoned |
| Battery storage project AH1-322, Miami County Battery storage |
90.0 MW | Withdrawn / abandoned |
| Solar project J1887, St. Martin Parish County Solar |
90.0 MW | Withdrawn / abandoned |
| Solar + storage project AG2-606, Perry County Solar + storage ยท North Corners Energy, LLC |
89.0 MW | Withdrawn / abandoned |
| Solar project AG2-461, New Kent County Solar |
88.0 MW | Withdrawn / abandoned |
| Solar project AG2-170, Wayne County Solar |
88.0 MW | Withdrawn / abandoned |
| Solar project J2264, Prairie County Solar |
88.0 MW | Withdrawn / abandoned |
| Battery storage project Q408, Maricopa County Battery storage |
88.0 MW | Withdrawn / abandoned |
| Hemlock Hollow Wind Onshore wind ยท Liberty Renewables Inc. |
87.9 MW | Withdrawn / abandoned |
| Solar with Battery Solar + storage |
87.0 MW | Withdrawn / abandoned |
| Battery storage project AH1-474, Crawford County Battery storage |
87.0 MW | Withdrawn / abandoned |
| Cuba Wind Project Onshore wind ยท SWEB Development USA, LLC |
86.5 MW | Withdrawn / abandoned |
| Solar project AH1-009, Dekalb County Solar |
86.0 MW | Withdrawn / abandoned |
| Solar project AH1-402, Indiana County Solar |
85.0 MW | Withdrawn / abandoned |
| Solar project AG2-508, Greensville County Solar |
85.0 MW | Withdrawn / abandoned |
| Solar project AH1-270, Franklin County Solar |
85.0 MW | Withdrawn / abandoned |
| St. Regis River Solar + storage ยท BW Solar Holding |
85.0 MW | Withdrawn / abandoned |
| Solar project AG2-521, Fluvanna County Solar |
85.0 MW | Withdrawn / abandoned |
| Solar + storage project 613, Elmore County Solar + storage |
85.0 MW | Withdrawn / abandoned |
| Solar project AG2-118, Clermont County Solar |
84.0 MW | Withdrawn / abandoned |
| Battery storage project AH1-481, White County Battery storage |
84.0 MW | Withdrawn / abandoned |
| Solar project J1950, Gibson County Solar |
83.2 MW | Withdrawn / abandoned |
| Solar project AG2-222, Rush County Solar |
83.0 MW | Withdrawn / abandoned |
| Battery storage project AH1-479, St. Joseph County Battery storage |
82.0 MW | Withdrawn / abandoned |
| Helix Storage Battery storage |
81.6 MW | Withdrawn / abandoned |
| Solar project GEN-2021-SR1, Seminole County Solar |
81.6 MW | Withdrawn / abandoned |
| Echelon Solar Solar + storage ยท Echelon Solar LLC |
80.0 MW | Withdrawn / abandoned |
| Solar project IC-983, Mobile County Solar |
80.0 MW | Withdrawn / abandoned |
| Solar + storage project IC-998, Baldwin County Solar + storage |
80.0 MW | Withdrawn / abandoned |
Capacity in the queue by state
Click a state to drill down.
By grid region
ISO/RTO markets and the non-ISO West and Southeast.
- CAISO (California)220 ยท 82.8 GW
- West (non-ISO utilities)339 ยท 78.3 GW
- PJM (Mid-Atlantic, Midwest)819 ยท 65.0 GW
- MISO (Midcontinent)267 ยท 38.5 GW
- NYISO (New York)149 ยท 23.5 GW
- Southeast (non-ISO utilities)123 ยท 16.3 GW
- ERCOT (Texas)77 ยท 13.4 GW
- SPP (Southwest Power Pool)70 ยท 13.1 GW
- ISO-NE (New England)85 ยท 8,317 MW
Requests by year joined
Capacity of requests in this view, by the year they entered the queue. Click a year.
Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines ยท Planned power plants (EIA)