🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › California

SOLAR + STORAGE · CAISO

Sweetbrier Hybrid Solar

Sweetbrier Hybrid Solar is a 90.8 MW solar + storage request withdrawn in the CAISO interconnection queue, in Monterey County, California, connecting to PGAE.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Apr 2021 (completed)
  2. Withdrawn / abandonedAug 2023 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
1974
Grid region
CAISO (California)
Utility / transmission owner
PGAE
Connection point (POI)
California Flats Switching Station 230 kV
Location
Monterey County, California
Technology
Solar: 60.6 MW · Battery: 30.2 MW
Total requested
90.8 MW
Service type
Network resource (NRIS)
Study phase
System Impact Study
Queue status
Withdrawn
Entered queue
15 April 2021
Proposed online date
November 2024
Withdrawn
August 2023

Location

Marker shows the centre of Monterey County; the queue data does not give exact sites.

Power plants in California · Transmission lines in California

Other requests in Monterey County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem