United States βΊ Grid βΊ Interconnection queues βΊ Pennsylvania
SOLAR + STORAGE Β· PJMSolar + storage project AG2-606, Perry County
Solar + storage project AG2-606, Perry County is a 89.0 MW solar + storage request withdrawn in the PJM interconnection queue, in Perry County, Pennsylvania, connecting to PPL.
Queue statusWithdrawn / abandoned
- PlanningQueued Mar 2021 (completed)
- Withdrawn / abandonedJul 2025 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- AG2-606
- Grid region
- PJM (Mid-Atlantic, Midwest)
- Utility / transmission owner
- PPL
- Developer
- North Corners Energy, LLC
- Connection point (POI)
- Sunbury-Juniata 500 kV
- Location
- Perry County, Pennsylvania
- Technology
- Solar: 89.0 MW Β· Battery
- Total requested
- 89.0 MW
- Service type
- Network resource (NRIS)
- Study phase
- In Progress (unknown study)
- Queue status
- Withdrawn
- Entered queue
- 31 March 2021
- Proposed online date
- June 2024
- Withdrawn
- July 2025
Location
Marker shows the centre of Perry County; the queue data does not give exact sites.
Power plants in Pennsylvania Β· Transmission lines in Pennsylvania
Other requests in Perry County
- Greenwood Solar IISolar + storage Β· 96.2 MW Β· withdrawn
- Solar project AE2-215, Perry CountySolar Β· 60.0 MW Β· withdrawn
- Solar + storage project AG2-418, Perry CountySolar + storage Β· 40.0 MW Β· withdrawn
- Battery storage project AF1-295, Perry CountyBattery storage Β· 12.0 MW Β· withdrawn
- PE-Windy HillSolar + storage Β· 3.0 MW Β· withdrawn
- PE-DellvilleSolar + storage Β· 3.0 MW Β· withdrawn
- PE-Green ParkSolar + storage Β· 3.0 MW Β· withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem