Solar project AG2-170, Wayne County

Solar project AG2-170, Wayne County is a 88.0 MW solar request withdrawn in the PJM interconnection queue, in Wayne County, Indiana, connecting to AEP.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Feb 2021 (completed)
  2. Withdrawn / abandonedDec 2024 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
AG2-170
Grid region
PJM (Mid-Atlantic, Midwest)
Utility / transmission owner
AEP
Connection point (POI)
Whitewater Valley Power Station 69 kV
Location
Wayne County, Indiana
Technology
Solar: 88.0 MW
Total requested
88.0 MW
Service type
Network resource (NRIS)
Study phase
Feasibility Study
Queue status
Withdrawn
Entered queue
26 February 2021
Proposed online date
December 2022
Withdrawn
December 2024

Location

Marker shows the centre of Wayne County; the queue data does not give exact sites.

Power plants in Indiana Β· Transmission lines in Indiana

Other requests in Wayne County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem