United States β€Ί Grid β€Ί Interconnection queues β€Ί Mississippi

SOLAR Β· MISO

Solar project J2023, Amite County

Solar project J2023, Amite County is a 94.1 MW solar request withdrawn in the MISO interconnection queue, in Amite County, Mississippi, connecting to ENTERGY MISSISSIPPI, LLC..

Queue statusWithdrawn / abandoned
  1. PlanningQueued Aug 2021 (completed)
  2. Withdrawn / abandonedOct 2023 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
J2023
Grid region
MISO (Midcontinent)
Utility / transmission owner
ENTERGY MISSISSIPPI, LLC.
Connection point (POI)
Gloster to Liberty 138 kV
Location
Amite County, Mississippi
Technology
Solar: 94.1 MW
Total requested
94.1 MW
Service type
Network resource (NRIS)
Study phase
Study Phase: GIA In Process; Post GIA Status: Not Started
Queue status
Withdrawn
Entered queue
26 August 2021
Proposed online date
April 2024
Withdrawn
October 2023

Location

Marker shows the centre of Amite County; the queue data does not give exact sites.

Power plants in Mississippi Β· Transmission lines in Mississippi

Other requests in Amite County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem