πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues β€Ί Virginia

SOLAR Β· PJM

Solar project AG2-168, Russell County

Solar project AG2-168, Russell County is a 95.0 MW solar request withdrawn in the PJM interconnection queue, in Russell County, Virginia, connecting to AEP.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Feb 2021 (completed)
  2. Withdrawn / abandonedDec 2024 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
AG2-168
Grid region
PJM (Mid-Atlantic, Midwest)
Utility / transmission owner
AEP
Connection point (POI)
Clinch River-Copper Ridge 138 kV
Location
Russell County, Virginia
Technology
Solar: 95.0 MW
Total requested
95.0 MW
Service type
Network resource (NRIS)
Study phase
Feasibility Study
Queue status
Withdrawn
Entered queue
26 February 2021
Proposed online date
December 2022
Withdrawn
December 2024

Location

Marker shows the centre of Russell County; the queue data does not give exact sites.

Power plants in Virginia Β· Transmission lines in Virginia

Other requests in Russell County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem