Withdrawn queue requests in the USA — page 216

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown24,2054,519.8 GW
Active in queue2,001.0 GW9,187 requests
Agreement signed423.2 GW2,141 requests
Withdrawn24,2054,519.8 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

24,205 requests · page 216 of 485
ProjectCapacityStatusLocationRegionQueuedOnline
Wood Street Battery Storage
Battery storage · Wood Street Battery Storage LLC
110 MWWithdrawn / abandoned Putnam, NYNYISO Mar 2021
Solar + storage project AD1-029, Halifax County
Solar + storage
110 MWWithdrawn / abandoned Halifax, NCPJM Jul 2017target 2019
Onshore wind project J2843, Hendricks County
Onshore wind
110 MWWithdrawn / abandoned Hendricks, INMISO Sep 2022target 2025
Margarita Storage
Battery storage · Sturgeon Pool BESS, LLC
110 MWWithdrawn / abandoned Ulster, NYNYISO Sep 2024
Las Hermanas BESS
Battery storage
110 MWWithdrawn / abandoned Shasta, CACAISO May 2016target 2019
Solar + storage project IC-1045, Stone County
Solar + storage
110 MWWithdrawn / abandoned Stone, MSSoutheast Jul 2022
Other project 120, Lake County
Other · Masked
110 MWWithdrawn / abandoned Lake, FLSoutheast Jun 2013target 1993
Solar + storage project 544, Robertson County
Solar + storage
110 MWWithdrawn / abandoned Robertson, TNSoutheast Apr 2023target 2028
Solar + storage project C2-155, Uinta County
Solar + storage
110 MWWithdrawn / abandoned Uinta, WYWest May 2022target 2026
Onshore wind project S44, Mifflin County
Onshore wind
110 MWWithdrawn / abandoned Mifflin, PAPJM May 2007target 2009
Solar project J1947, Fountain County
Solar
110 MWWithdrawn / abandoned Fountain, INMISO Mar 2022target 2025
Solar project J3348, Marshall County
Solar
110 MWWithdrawn / abandoned Marshall, INMISO Apr 2024target 2028
Solar project IC-1163, Perry County
Solar
110 MWWithdrawn / abandoned Perry, MSSoutheast Aug 2023target 2026
Solar
Solar
110 MWWithdrawn / abandoned Carroll, NHISO-NE Oct 2019target 2025
Solar + storage project J3068, St. Helena Parish County
Solar + storage
110 MWWithdrawn / abandoned St. Helena Parish, LAMISO Sep 2022target 2026
Solar project 2021-G1
Solar
110 MWWithdrawn / abandoned West Jan 2021target 2023
Battery storage project AH1-768, Blackford County
Battery storage · RWE Solar Development, LLC
110 MWWithdrawn / abandoned Blackford, INPJM target 2029
Onshore wind project 863, Carbon County
Onshore wind
110 MWWithdrawn / abandoned Carbon, WYWest Apr 2017target 2020
Solar project GEN-2021-062, Lea County
Solar
110 MWWithdrawn / abandoned Lea, NMSPP Apr 20212025
Solar + storage project IC-941, Perry County
Solar + storage
110 MWWithdrawn / abandoned Perry, MSSoutheast Mar 2021target 2024
Onshore wind project G0402, Sherman County
Onshore wind
110 MWWithdrawn / abandoned Sherman, ORWest Jan 2010target 2013
Gas project J427, Livingston County
Gas
110 MWWithdrawn / abandoned Livingston, MIMISO Nov 2014
Other project IC-219, Clay County
Other
110 MWWithdrawn / abandoned Clay, GASoutheast Mar 2007
Solar + storage project AF2-204, Grant County
Solar + storage
110 MWWithdrawn / abandoned Grant, INPJM Mar 2020target 2023
Solar project GEN-2017-064, Oglala Lakota County
Solar
110 MWWithdrawn / abandoned Oglala Lakota, SDSPP May 2017target 2023
Other project U1-030, Atlantic County
Other
110 MWWithdrawn / abandoned Atlantic, NJPJM Feb 2008target 2013
Solar + storage project 551, Gibson County
Solar + storage
110 MWWithdrawn / abandoned Gibson, TNSoutheast May 2023target 2024
FRV Diamond Valley Solar
Solar
110 MWWithdrawn / abandoned Riverside, CACAISO Feb 2010target 2013
Solar project AH1-550, Licking County
Solar
110 MWWithdrawn / abandoned Licking, OHPJM Sep 2021target 2025
Solar + storage project GEN-2023-148, Jackson County
Solar + storage
110 MWWithdrawn / abandoned Jackson, OKSPP Oct 2023target 2027
Other project U1-029, Cumberland County
Other
110 MWWithdrawn / abandoned Cumberland, NJPJM Feb 2008target 2012
Pio Pico 2
Gas
110 MWWithdrawn / abandoned San Diego, CACAISO Apr 2013target 2017
Gas project G249, Shawano County
Gas
110 MWWithdrawn / abandoned Shawano, WIMISO Aug 2002target 2003
Solar + storage project AH2-211, St. Joseph County
Solar + storage
110 MWWithdrawn / abandoned St. Joseph, INPJM Mar 2022target 2025
Battery storage project AH1-598, Ashland County
Battery storage
110 MWWithdrawn / abandoned Ashland, OHPJM Sep 2021target 2025
Solar project LGE-GIS-2019-001, Washington County
Solar
110 MWWithdrawn / abandoned Washington, KYSoutheast Jan 2019target 2023
Battery storage project C2-164, Salt Lake County
Battery storage
110 MWWithdrawn / abandoned Salt Lake, UTWest May 2022target 2025
Gas project J3587, Jefferson County
Gas
110 MWWithdrawn / abandoned Jefferson, TXMISO Apr 2024target 2027
Solar project AF2-090, Hardin County
Solar
110 MWWithdrawn / abandoned Hardin, KYPJM Feb 2020target 2022
Onshore wind project G0206, Union County
Onshore wind
110 MWWithdrawn / abandoned Union, ORWest Jun 2005target 2008
Solar project AH1-597, Ashland County
Solar
110 MWWithdrawn / abandoned Ashland, OHPJM Sep 2021target 2025
Solar project 956283, Chesterfield County
Solar · Masked
110 MWWithdrawn / abandoned Chesterfield, SCSoutheast Jun 2024
Gas project X4-018, Hudson County
Gas
110 MWWithdrawn / abandoned Hudson, NJPJM Nov 2011target 2015
Solar project J2858, Acadia Parish County
Solar
110 MWWithdrawn / abandoned Acadia Parish, LAMISO Sep 2022target 2025
Solar project Q30, Maricopa County
Solar
110 MWWithdrawn / abandoned Maricopa, AZWest Jul 2007target 2011
Onshore wind project G702, Worth County
Onshore wind
110 MWWithdrawn / abandoned Worth, IAMISO Nov 2006target 2007
DRY Creek Solar
Solar
110 MWWithdrawn / abandoned Kern, CACAISO Apr 2018target 2022
Pio Pico Unit 4
Gas
110 MWWithdrawn / abandoned San Diego, CACAISO Apr 2015target 2018
Solar project IA-PNM-2017-21, Mckinley County
Solar
110 MWWithdrawn / abandoned Mckinley, NMWest Oct 2017target 2022
Combustion Turbine
Gas
110 MWWithdrawn / abandoned Fairfield, CTISO-NE Feb 2015target 2018
Page 216 of 485

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)