GAS Β· ISO-NE

Combustion Turbine

Combustion Turbine is a 110 MW gas request withdrawn in the ISO-NE interconnection queue, in Fairfield County, Connecticut.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Feb 2015 (completed)
  2. Withdrawn / abandonedMar 2016 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
521
Grid region
ISO-NE (New England)
Connection point (POI)
CL&P (Eversource) 115 kV Middle River Substation
Location
Fairfield County, Connecticut
Technology
Gas: 110 MW Β· Oil
Total requested
110 MW
Service type
Network resource (NRIS)
Study phase
Feasibility Study
Queue status
Withdrawn
Entered queue
17 February 2015
Proposed online date
May 2018
Withdrawn
March 2016

Location

No county location in the queue data.