SOLAR Β· MISO

Solar project J3348, Marshall County

Solar project J3348, Marshall County is a 110 MW solar request withdrawn in the MISO interconnection queue, in Marshall County, Indiana, connecting to NORTHERN INDIANA PUBLIC SERVICE COMPANY.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Apr 2024 (completed)
  2. Withdrawn / abandonedSep 2025 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
J3348
Grid region
MISO (Midcontinent)
Utility / transmission owner
NORTHERN INDIANA PUBLIC SERVICE COMPANY
Connection point (POI)
PLYMOUTH - KOSCIUSKO & LEESBURG & KOSCIUSKO CO REMC - NORTHWEST 138.0kV
Location
Marshall County, Indiana
Technology
Solar: 110 MW
Total requested
110 MW
Service type
Network resource (NRIS)
Study phase
Study Phase: DPP 1
Queue status
Withdrawn
Entered queue
17 April 2024
Proposed online date
September 2028
Withdrawn
September 2025

Location

Marker shows the centre of Marshall County; the queue data does not give exact sites.

Power plants in Indiana Β· Transmission lines in Indiana

Other requests in Marshall County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem