United States › Grid › Interconnection queues

OCTARY USA · INTERCONNECTION QUEUES

Withdrawn queue requests in the USA (2022 requests) — page 21

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown1,886378.9 GW
Active in queue299.4 GW1,514 requests
Agreement signed43.0 GW228 requests
Withdrawn1,886378.9 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

1,886 requests · page 21 of 38
ProjectCapacityStatusLocationRegionQueuedOnline
Solar Generation Jennison Revitalization Facility
Solar · Solar Generation
118 MWWithdrawn / abandoned Chenango, NYNYISO Feb 2022
Battery Storage
Battery storage
117 MWWithdrawn / abandoned Bristol, MAISO-NE Dec 2022target 2027
Highland Storage
Battery storage · Origis Development
115 MWWithdrawn / abandoned Ulster, NYNYISO Nov 2022
Solar project G0835, Harney County
Solar
115 MWWithdrawn / abandoned Harney, ORWest Dec 2022target 2027
Solar project AH2-212, Madison County
Solar
115 MWWithdrawn / abandoned Madison, OHPJM Mar 2022target 2026
Battery storage project J2621, St. Croix County
Battery storage
115 MWWithdrawn / abandoned St. Croix, WIMISO Sep 2022target 2027
Solar + storage project J3092, Bolivar County
Solar + storage
115 MWWithdrawn / abandoned Bolivar, MSMISO Sep 2022target 2026
Solar + storage project C2-160, Iron County
Solar + storage
115 MWWithdrawn / abandoned Iron, UTWest May 2022target 2026
Solar + storage project J3094, Daviess County
Solar + storage
115 MWWithdrawn / abandoned Daviess, INMISO Sep 2022target 2026
Battery storage project J2365, Portage County
Battery storage
115 MWWithdrawn / abandoned Portage, WIMISO Sep 2022target 2030
NY Amsterdam 152 Persons Rd Storage
Battery storage · Bluewave Storage Origination LLC
115 MWWithdrawn / abandoned Montgomery, NYNYISO Oct 2022
Solar project J2358, Madison County
Solar
114 MWWithdrawn / abandoned Madison, MSMISO Sep 2022target 2024
Solar project 569238, Duplin County
Solar · Masked
112 MWWithdrawn / abandoned Duplin, NCSoutheast Jun 2022
Solar + storage project 523, Lake County
Solar + storage
110 MWWithdrawn / abandoned Lake, ALSoutheast Oct 2022target 2026
Morris Sole Solar
Solar · EDF renewables development inc.
110 MWWithdrawn / abandoned Livingston, NYNYISO Feb 2022
Solar + storage project J2832, East Carroll Parish County
Solar + storage
110 MWWithdrawn / abandoned East Carroll Parish, LAMISO Sep 2022target 2025
Solar project J3180, De Soto Parish County
Solar
110 MWWithdrawn / abandoned De Soto Parish, LAMISO Sep 2022target 2026
Yellow Feather Energy Center
Solar · Yellow Feather Energy Center
110 MWWithdrawn / abandoned Montgomery, NYNYISO Dec 2022
Onshore wind project J2843, Hendricks County
Onshore wind
110 MWWithdrawn / abandoned Hendricks, INMISO Sep 2022target 2025
Solar + storage project IC-1045, Stone County
Solar + storage
110 MWWithdrawn / abandoned Stone, MSSoutheast Jul 2022
Solar + storage project C2-155, Uinta County
Solar + storage
110 MWWithdrawn / abandoned Uinta, WYWest May 2022target 2026
Solar project J1947, Fountain County
Solar
110 MWWithdrawn / abandoned Fountain, INMISO Mar 2022target 2025
Solar + storage project J3068, St. Helena Parish County
Solar + storage
110 MWWithdrawn / abandoned St. Helena Parish, LAMISO Sep 2022target 2026
Solar + storage project AH2-211, St. Joseph County
Solar + storage
110 MWWithdrawn / abandoned St. Joseph, INPJM Mar 2022target 2025
Battery storage project C2-164, Salt Lake County
Battery storage
110 MWWithdrawn / abandoned Salt Lake, UTWest May 2022target 2025
Solar project J2858, Acadia Parish County
Solar
110 MWWithdrawn / abandoned Acadia Parish, LAMISO Sep 2022target 2025
Onshore wind project J3222, Moultrie County
Onshore wind
109 MWWithdrawn / abandoned Moultrie, ILMISO Sep 2022target 2025
Solar project PIS007, Bonneville County
Solar
107 MWWithdrawn / abandoned Bonneville, IDWest May 2022target 2025
Harlem River Yards Energy Storage
Battery storage · NY Power Authority
107 MWWithdrawn / abandoned Bronx, NYNYISO Jul 2022
Battery Storage
Battery storage
107 MWWithdrawn / abandoned Windham, CTISO-NE Sep 2022target 2026
Solar project C2-166, Bonneville County
Solar
107 MWWithdrawn / abandoned Bonneville, IDWest May 2022target 2025
Solar project J2622, Drew County
Solar
107 MWWithdrawn / abandoned Drew, ARMISO Sep 2022target 2027
Solar project J3036, Lonoke County
Solar
105 MWWithdrawn / abandoned Lonoke, ARMISO Sep 2022target 2026
Solar project J2483, Amite County
Solar
105 MWWithdrawn / abandoned Amite, MSMISO Sep 2022target 2025
Solar project J2467, Evangeline Parish County
Solar
105 MWWithdrawn / abandoned Evangeline Parish, LAMISO Sep 2022target 2026
Solar project J2361, Perry County
Solar
105 MWWithdrawn / abandoned Perry, ARMISO Sep 2022target 2026
Battery storage project GEN-2022-SR1, Burke County
Battery storage
104 MWWithdrawn / abandoned Burke, NDSPP Mar 2022target 2022
NY Greenport 85 Middle Rd Storage
Battery storage · Bluewave Storage Origination LLC
104 MWWithdrawn / abandoned Columbia, NYNYISO Jun 2022
Hive Hollows Storage
Other · KCE TX 27, LLC
104 MWWithdrawn / abandoned Bell, TXERCOT Jan 2022target 2026
Gowanus Energy Storage
Battery storage · NY Power Authority
103 MWWithdrawn / abandoned Kings, NYNYISO Jul 2022
Papley Storage
Battery storage · Papley Storage, LLC
103 MWWithdrawn / abandoned ERCOT Dec 2022target 2029
Hoffman Falls Wind 2
Onshore wind · Liberty Renewables Inc.
103 MWWithdrawn / abandoned Madison, NYNYISO Feb 2022
Solar plus Battery
Solar + storage
102 MWWithdrawn / abandoned Cheshire, NHISO-NE Sep 2022target 2027
Perry Creek Solar SLF
Solar · Perry Creek Solar, LLC
102 MWWithdrawn / abandoned ERCOT Dec 2022target 2027
Albatross Solar
Solar · Albatross Solar, LLC
101 MWWithdrawn / abandoned Mclennan, TXERCOT May 2022target 2025
Solar project J2702, Fulton County
Solar
101 MWWithdrawn / abandoned Fulton, ILMISO Sep 2022target 2027
Battery storage project GEN-2022-SR2
Battery storage
101 MWWithdrawn / abandoned SPP Mar 2022
Solar project GEN-2022-SR3
Solar
100 MWWithdrawn / abandoned SPP Mar 2022
Solar project GEN-2023-SR6, Wayne County
Solar
100 MWWithdrawn / abandoned Wayne, NESPP Dec 20222024
Battery storage project 22-115, Washington County
Battery storage
100 MWWithdrawn / abandoned Washington, ORWest Oct 2022target 2024
Page 21 of 38

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)