πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues

BATTERY STORAGE Β· ERCOT

Papley Storage

Papley Storage is a 103 MW battery storage request withdrawn in the ERCOT interconnection queue.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Dec 2022 (completed)
  2. Withdrawn / abandoned (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
25INR0252
Grid region
ERCOT (Texas)
Developer
Papley Storage, LLC
Connection point (POI)
Tap 138 kV line 8692 Maverick - 8255 Hamilton Road
Technology
Battery: 103 MW
Total requested
103 MW
Study phase
FIS
Queue status
Withdrawn
Entered queue
7 December 2022
Proposed online date
March 2029

Location

No county location in the queue data.

Power plants in Β· Transmission lines in

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem