πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues β€Ί Nebraska

SOLAR Β· SPP

Solar project GEN-2023-SR6, Wayne County

Solar project GEN-2023-SR6, Wayne County is a 100 MW solar request withdrawn in the SPP interconnection queue, in Wayne County, Nebraska, connecting to NPPD.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Dec 2022 (completed)
  2. Withdrawn / abandonedOct 2023 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. OperatingDec 2024 (not reached)
  6. Closed (not reached)

Request details

Queue ID
GEN-2023-SR6
Grid region
SPP (Southwest Power Pool)
Utility / transmission owner
NPPD
Connection point (POI)
Hoskins 345 kV Substation
Location
Wayne County, Nebraska
Technology
Solar: 100 MW
Total requested
100 MW
Service type
Energy only (ERIS)
Study phase
WITHDRAWN
Queue status
Withdrawn
Entered queue
16 December 2022
Proposed online date
December 2024
Came online
December 2024
Withdrawn
October 2023

Location

Marker shows the centre of Wayne County; the queue data does not give exact sites.

Power plants in Nebraska Β· Transmission lines in Nebraska

Other requests in Wayne County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem