United States βΊ Grid βΊ Interconnection queues βΊ Nebraska
ONSHORE WIND Β· SPPOnshore wind project GEN-2018-012, Wayne County
Onshore wind project GEN-2018-012, Wayne County is a 74.1 MW onshore wind request withdrawn in the SPP interconnection queue, in Wayne County, Nebraska, connecting to NPPD.
Queue statusWithdrawn / abandoned
- PlanningQueued Apr 2018 (completed)
- Withdrawn / abandonedFeb 2024 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- OperatingNov 2025 (not reached)
- Closed (not reached)
Request details
- Queue ID
- GEN-2018-012
- Grid region
- SPP (Southwest Power Pool)
- Utility / transmission owner
- NPPD
- Connection point (POI)
- Antelope 345kV Substation
- Location
- Wayne County, Nebraska
- Technology
- Wind: 74.1 MW
- Total requested
- 74.1 MW
- Service type
- NRIS and ERIS
- Study phase
- WITHDRAWN
- Queue status
- Withdrawn
- Entered queue
- 27 April 2018
- Proposed online date
- November 2025
- Came online
- November 2025
- Withdrawn
- February 2024
Location
Marker shows the centre of Wayne County; the queue data does not give exact sites.
Other requests in Wayne County
- Onshore wind project GEN-2017-201, Wayne CountyOnshore wind Β· 250 MW Β· agreement signed
- Battery storage project GEN-2023-SR7, Wayne CountyBattery storage Β· 135 MW Β· in study
- Onshore wind project GEN-2016-043, Wayne CountyOnshore wind Β· 230 MW Β· built
- Onshore wind project GEN-2015-007, Wayne CountyOnshore wind Β· 160 MW Β· built
- Onshore wind project GEN-2011-027, Wayne CountyOnshore wind Β· 120 MW Β· built
- Onshore wind project GEN-2014-055, Wayne CountyOnshore wind Β· 160 MW Β· withdrawn
- Onshore wind project GEN-2013-039, Wayne CountyOnshore wind Β· 160 MW Β· withdrawn
- Solar project GEN-2023-SR6, Wayne CountySolar Β· 100 MW Β· withdrawn
- Onshore wind project GEN-2006-038N011, Wayne CountyOnshore wind Β· 100 MW Β· withdrawn
- Onshore wind project GEN-2010-026, Wayne CountyOnshore wind Β· 99.0 MW Β· withdrawn
- Battery storage project GEN-2022-044, Wayne CountyBattery storage Β· 80.0 MW Β· withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem