United States βΊ Grid βΊ Interconnection queues βΊ Arkansas
SOLAR Β· MISOSolar project J2361, Perry County
Solar project J2361, Perry County is a 105 MW solar request withdrawn in the MISO interconnection queue, in Perry County, Arkansas, connecting to ENTERGY ARKANSAS.
Queue statusWithdrawn / abandoned
- PlanningQueued Sep 2022 (completed)
- Withdrawn / abandonedMar 2023 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- J2361
- Grid region
- MISO (Midcontinent)
- Utility / transmission owner
- ENTERGY ARKANSAS
- Connection point (POI)
- AECC Oppelo 161 kV Substation
- Location
- Perry County, Arkansas
- Technology
- Solar: 105 MW
- Total requested
- 105 MW
- Service type
- Network resource (NRIS)
- Study phase
- Study Phase: DPP 2; Post GIA Status: Not Started
- Queue status
- Withdrawn
- Entered queue
- 15 September 2022
- Proposed online date
- May 2026
- Withdrawn
- March 2023
Location
Marker shows the centre of Perry County; the queue data does not give exact sites.
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem