🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › New York

BATTERY STORAGE · NYISO

Highland Storage

Highland Storage is a 115 MW battery storage request withdrawn in the NYISO interconnection queue, in Ulster County, New York, connecting to CHG&E.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Nov 2022 (completed)
  2. Withdrawn / abandoned (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
1472
Grid region
NYISO (New York)
Utility / transmission owner
CHG&E
Developer
Origis Development
Connection point (POI)
Marlboro 115 kV Substation
Location
Ulster County, New York
Technology
Battery: 115 MW
Total requested
115 MW
Queue status
Withdrawn
Entered queue
23 November 2022

Location

Marker shows the centre of Ulster County; the queue data does not give exact sites.

Power plants in New York · Transmission lines in New York

Other requests in Ulster County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem