BATTERY STORAGE · NYISO

Magruder BESS

Magruder BESS is a 20.0 MW battery storage request in interconnection study in the NYISO interconnection queue, in Ulster County, New York, connecting to CHG&E.

Queue statusIn planning
  1. PlanningQueued Jul 2018 (current stage)
  2. ConsentedApr 2021 (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Apr 2028 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
744
Grid region
NYISO (New York)
Utility / transmission owner
CHG&E
Developer
Mitchell Energy Facility, LLC
Connection point (POI)
East Walden - Modena 115kV
Location
Ulster County, New York
Technology
Battery: 20.0 MW
Total requested
20.0 MW
Study phase
SIS, FS
Queue status
Active
Entered queue
18 July 2018
Agreement signed
6 April 2021
Proposed online date
April 2028

Location

Marker shows the centre of Ulster County; the queue data does not give exact sites.

Power plants in New York · Transmission lines in New York

Other requests in Ulster County