United States βΊ Grid βΊ Interconnection queues βΊ Texas
SOLAR Β· ERCOTAlbatross Solar
Albatross Solar is a 101 MW solar request withdrawn in the ERCOT interconnection queue, in Mclennan County, Texas.
Queue statusWithdrawn / abandoned
- PlanningQueued May 2022 (completed)
- Withdrawn / abandonedNov 2024 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- 25INR0070
- Grid region
- ERCOT (Texas)
- Developer
- Albatross Solar, LLC
- Connection point (POI)
- Tap 138kV 165 Windsor Switch - 161 McGregor
- Location
- Mclennan County, Texas
- Technology
- Solar: 101 MW
- Total requested
- 101 MW
- Study phase
- FIS Complete
- Queue status
- Withdrawn
- Entered queue
- 15 May 2022
- Proposed online date
- August 2025
- Withdrawn
- November 2024
Location
Marker shows the centre of Mclennan County; the queue data does not give exact sites.
Other requests in Mclennan County
- Jaguar SolarSolar + storage Β· 301 MW Β· agreement signed
- Prairie Hill WindOnshore wind Β· 297 MW Β· agreement signed
- Cibeles SolarSolar Β· 252 MW Β· agreement signed
- Tokio SolarSolar Β· 171 MW Β· agreement signed
- Pepper Solar FarmSolar Β· 121 MW Β· agreement signed
- Neutron StorageBattery storage Β· 105 MW Β· agreement signed
- Axtell BESSBattery storage Β· 307 MW Β· in study
- PowerVault BESSBattery storage Β· 255 MW Β· in study
- Finch StorageBattery storage Β· 201 MW Β· in study
- Albatross BESS 2Battery storage Β· 160 MW Β· in study
- Albatross BESSBattery storage Β· 50.4 MW Β· in study
- Graphic Packaging GasGas Β· 43.4 MW Β· in study
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem